face26
2020-04-20 16:20:17
- #1
600k with 4,800€ net you can already get currently. Depending on how contractually the special payment is fixed, even very easily.
Points you might stumble over (not necessarily):
Just not planned? What if yes?
450 sqm * 500€/sqm = 225,000 -> 250,000 with incidental acquisition costs
150 * 2,500/sqm = 375,000
Garage = 30,000
Outdoor facilities = 20,000
Construction incidental costs = 40,000
Total = 715,000
Buffer not yet taken into account. That would be roughly your equity.
Here people like to calculate with EUR 2,000/sqm. But the number is sometimes a bit tight depending on the region. Heavily dependent on your desired standard. The Freiburg region is rather an expensive region. I am not among those who think that building prices are falling due to Corona. Since you are still looking and don’t have a plot, until it is planned and so on, 2,500/sqm is not unrealistic.
The other points are just exemplary. Some make a carport for 10k, some outdoor facilities for 50k (sloping plots are for example “dangerous”).
Want to say the budget can quickly become too tight with the land prices.
Points you might stumble over (not necessarily):
No children planned.
Just not planned? What if yes?
As budget we have about 600,000 € for ~450 sqm land and 150 sqm (finished)
450 sqm * 500€/sqm = 225,000 -> 250,000 with incidental acquisition costs
150 * 2,500/sqm = 375,000
Garage = 30,000
Outdoor facilities = 20,000
Construction incidental costs = 40,000
Total = 715,000
Buffer not yet taken into account. That would be roughly your equity.
Here people like to calculate with EUR 2,000/sqm. But the number is sometimes a bit tight depending on the region. Heavily dependent on your desired standard. The Freiburg region is rather an expensive region. I am not among those who think that building prices are falling due to Corona. Since you are still looking and don’t have a plot, until it is planned and so on, 2,500/sqm is not unrealistic.
The other points are just exemplary. Some make a carport for 10k, some outdoor facilities for 50k (sloping plots are for example “dangerous”).
Want to say the budget can quickly become too tight with the land prices.