Hello everyone,
maybe some topics related to house construction are not that complex, or I am just making it harder than it is.
We have submitted our building application (in Berlin, prime plot) and now I want to apply for all utilities. Some questions have come up (probably typical beginner questions):
At the front of the street, electricity and water are available. I want to have the lines to the back where the house will be built installed only after the shell of the house is standing. Will construction electricity and construction water therefore be routed above ground from the street to the back?
Do cable TV and telephone connections have to be applied for early or is it sufficient to do this only after the house is completed?
My goal is to have to dig the path to the house at the back only once and then lay water, sewage, electricity, cable, and telephone all at once.
Is it correct that one pays the connection fee once (e.g., to the local network operator) and then again for the actual installation to the house or the connection to the house?
Sorry for these beginner questions :-)
Regards
maybe some topics related to house construction are not that complex, or I am just making it harder than it is.
We have submitted our building application (in Berlin, prime plot) and now I want to apply for all utilities. Some questions have come up (probably typical beginner questions):
At the front of the street, electricity and water are available. I want to have the lines to the back where the house will be built installed only after the shell of the house is standing. Will construction electricity and construction water therefore be routed above ground from the street to the back?
Do cable TV and telephone connections have to be applied for early or is it sufficient to do this only after the house is completed?
My goal is to have to dig the path to the house at the back only once and then lay water, sewage, electricity, cable, and telephone all at once.
Is it correct that one pays the connection fee once (e.g., to the local network operator) and then again for the actual installation to the house or the connection to the house?
Sorry for these beginner questions :-)