Announcement of shell construction completion for prefab house

  • Erstellt am 2016-06-05 13:19:17

Bader

2016-06-05 13:19:17
  • #1
When is the shell considered complete in a prefabricated house? In principle, the house is completely erected within a few days. I would have assumed that the shell is considered finished after that. I would have to inform the building authority of the date 2 weeks in advance, including the inspection by the chimney sweep. But the chimney is only built during the few days of the house assembly. How is this handled? We want to continue building as quickly as possible...
 

Bauexperte

2016-06-05 15:36:34
  • #2
Why do you have to take care of this and not your general contractor - in the case of complete contracting - or your architect in the case of individual trade contracting?

As a rule, the closed shell construction is meant - masonry, carpentry + roofer.

Rhenish regards
 

Bader

2016-06-05 22:11:33
  • #3
I am taking care of it because although I have a site manager (neither BU nor architect), I am taking care of it myself. It doesn’t matter anyway, I just want to know or gain experience with it. So, a prefabricated house with a chimney is built within a week (timber frame, windows, roof covered). After that, it should continue.
 

aheka

2016-06-09 10:30:38
  • #4
Hello,

we had the same problem.
After the house was set up, we contacted the [Schorni], who measured the chimney (determined suitability), sent the certificate by mail, then forwarded everything to the building authority. A short note explaining that due to prefabrication and partial rescheduling, the 14-day deadline cannot be met. We had no problems at all; when no response came after 1 1/2 weeks (interior work only after approval), we called and were told that we are not actually as far behind schedule as planned – we can proceed. The background of this statement was that when reporting the shell completion, we also had to include the shell measurement – this was one of the conditions of the building permit. The verbal agreement was also no problem afterwards during the building inspection – but in hindsight, I would insist on something in writing.
 

Similar topics
29.08.2013Prefabricated house (wood) vs solid construction (stone on stone)11
23.06.2014Prefabricated house or solid construction - what is your opinion?45
26.04.2015Semi-detached house architect or general contractor / prefabricated house or solid construction13
05.01.2016Chimney drawn incorrectly16
20.06.2016Building Authority Approval10
23.09.2016Architect and budget limit... insurance? possibilities25
11.02.2017Prefab house - yes or no?95
21.02.2017Renovate the core of the old house or build a prefab house?16
15.09.2017What can be done with a prefabricated house on your own?14
18.09.2018No offer for electrical work - must the shell construction be stopped?12
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
14.07.2019Costs for the shell construction of an office building16
21.12.2019Prefabricated house or solid house16
28.05.2020Buy a 25-year-old shell structure42
10.11.2020The architect is wrong with the estimates. And now?29
17.12.2022Realistic construction time for a bungalow?37
06.01.2023Solid house or prefabricated house? Semi-detached house, approx. 160 sqm, pros and cons22
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57
24.02.2025Construction Costs Shell/Turnkey Comparison39
21.03.2025New prefabricated house construction on existing basement, what funding options are available10

Oben