Advance Payment Plan Experiences

  • Erstellt am 2024-02-22 20:37:21

nedkelly

2024-02-22 20:37:21
  • #1
Hello everyone,

can you give me an assessment of the following installment payment schedule?

Conditions:
-Row house ~450k (+100k land)
-Prefabricated house 150 sqm
-Turnkey except for kitchen and lighting
-Wood frame kfw55
-Flat roof
-Single garage
-Windows, electricity, water, underfloor heating, screed, interior cladding, plaster paint, etc. are all installed only on site.


From the consumer construction contract:
...
The following installment payment schedule applies:
3% upon signing the contract
15% at the start of the solid construction work
20% at the start of house production in the factory hall
20% upon completion of house production in the factory hall
25% at the start of house assembly on the construction site
10% at the start of installation work (heating, sanitation, etc.)
5% upon completion of interior finishing
2% at final acceptance

Changes or overlaps in the order may be possible due to the construction process. In this case, changes to the payment steps will be timely reported to the client by the construction company.

Completion: 11 months after receipt of the building permit
Should the completion date be delayed due to force majeure (e.g. extraordinary weather or natural events) or other circumstances unknown at contract signing, the construction company cannot be held liable for any delay costs.

The construction company points out that it is neither obligated nor willing to participate in a dispute resolution procedure before a consumer arbitration board under the Consumer Arbitration Act.



Are such passages and high advance payments common? It seems very risky and strange to me.

Thank you very much for your feedback.
 

markusla

2024-02-22 21:00:24
  • #2
If payment were made after completion of each respective section, that would be fine. As it stands, you are advancing payment everywhere and would have paid nothing or even more in case of emergency.
 

Rübe1

2024-02-22 21:39:36
  • #3
So, you paid 58% and have a [Bodenplatte (?)] Then you paid 83% and don’t even have windows installed yet, if things go badly. Nothing more needs to be said. Tick, as in ticking off…
 

WilderSueden

2024-02-22 22:15:31
  • #4
Do not skimp on the completion guarantee in the payment plan under any circumstances. You pay a lot of money and still have no value on the construction site. Ideally, you would look for another provider. Payment at the start and with such a large advance is totally inappropriate, in my opinion.
 

xMisterDx

2024-02-22 22:24:49
  • #5


Even then, it would be a pure lottery... over 50% of the total amount would already be due when the company reports the completion of the prefabricated house parts in production.
But... how does the interested lay builder verify this? Even if you go there yourself. How do you know that you are shown the parts that will ultimately be used on your own construction site?
To someone who has no idea, you can fake anything... and that is exactly what happens... daily.
 

11ant

2024-02-22 23:41:04
  • #6

Start of the solid construction work in a wood frame panel "ready" house – do they mean the masonry of a basement?

And all that as a terraced house in a (covert?) developer project?
Do they believe you don’t read insolvency news about providers of market-oriented projects who are currently broadly in turmoil?



Withdrawal, yes, but another provider is difficult with developer terraced houses.
 

Similar topics
02.02.2009Building materials are stolen at the construction site12
28.05.2015Round window - dissatisfied with the interior reveal16
18.01.2016Payment of final installment and acceptance44
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
08.08.2016Payment before or after completion of the construction phase?51
10.09.2016Construction financing and contract with the developer24
28.02.2017Are securities customary for completion and warranty?24
19.08.2018Strategically well-planned handover completion under building supervision11
11.10.2018Waste on the construction site - What is tolerable?138
08.10.2019Terraced house as a homeowners' association or better alternative13
29.09.2020Building permit before completion of development31
23.03.2020Curfew: Am I still allowed to go to the construction site in Bavaria?73
09.04.2020Visit the construction site for ventilation?17
18.10.2020Window & door installation not compliant with standards28
19.08.2021House building - an eternal construction site?33
14.11.2021Sell an apartment from a two-family house immediately after completion34
01.07.2022Construction delay without completion. The house simply is not finished21
21.09.2022Camera / mobile phone for documentation in the workshop or construction site13

Oben