nedkelly
2024-02-22 20:37:21
- #1
Hello everyone,
can you give me an assessment of the following installment payment schedule?
Conditions:
-Row house ~450k (+100k land)
-Prefabricated house 150 sqm
-Turnkey except for kitchen and lighting
-Wood frame kfw55
-Flat roof
-Single garage
-Windows, electricity, water, underfloor heating, screed, interior cladding, plaster paint, etc. are all installed only on site.
From the consumer construction contract:
...
The following installment payment schedule applies:
3% upon signing the contract
15% at the start of the solid construction work
20% at the start of house production in the factory hall
20% upon completion of house production in the factory hall
25% at the start of house assembly on the construction site
10% at the start of installation work (heating, sanitation, etc.)
5% upon completion of interior finishing
2% at final acceptance
Changes or overlaps in the order may be possible due to the construction process. In this case, changes to the payment steps will be timely reported to the client by the construction company.
…
Completion: 11 months after receipt of the building permit
Should the completion date be delayed due to force majeure (e.g. extraordinary weather or natural events) or other circumstances unknown at contract signing, the construction company cannot be held liable for any delay costs.
…
The construction company points out that it is neither obligated nor willing to participate in a dispute resolution procedure before a consumer arbitration board under the Consumer Arbitration Act.
Are such passages and high advance payments common? It seems very risky and strange to me.
Thank you very much for your feedback.
can you give me an assessment of the following installment payment schedule?
Conditions:
-Row house ~450k (+100k land)
-Prefabricated house 150 sqm
-Turnkey except for kitchen and lighting
-Wood frame kfw55
-Flat roof
-Single garage
-Windows, electricity, water, underfloor heating, screed, interior cladding, plaster paint, etc. are all installed only on site.
From the consumer construction contract:
...
The following installment payment schedule applies:
3% upon signing the contract
15% at the start of the solid construction work
20% at the start of house production in the factory hall
20% upon completion of house production in the factory hall
25% at the start of house assembly on the construction site
10% at the start of installation work (heating, sanitation, etc.)
5% upon completion of interior finishing
2% at final acceptance
Changes or overlaps in the order may be possible due to the construction process. In this case, changes to the payment steps will be timely reported to the client by the construction company.
…
Completion: 11 months after receipt of the building permit
Should the completion date be delayed due to force majeure (e.g. extraordinary weather or natural events) or other circumstances unknown at contract signing, the construction company cannot be held liable for any delay costs.
…
The construction company points out that it is neither obligated nor willing to participate in a dispute resolution procedure before a consumer arbitration board under the Consumer Arbitration Act.
Are such passages and high advance payments common? It seems very risky and strange to me.
Thank you very much for your feedback.