summoner
2025-01-04 13:51:08
- #1
Hi,
we are currently in the process of building a house with a general contractor who is also "responsible" for the basement.
A solid house is being built, fully basemented with a [Weiße Wanne], whereby the basement, which consists of WU concrete, is completely "in the ground," i.e., not, for example, partially exposed. In the basement itself, there are waterproof light shafts in every room. The soil survey confirms no pressing groundwater.
The WU construction is/was carried out according to the contract as follows (excerpt only):
Approx. 24 cm thick reinforced concrete walls made of in-situ concrete, 30 cm thick reinforced concrete floor slab with reinforcement, PE foil as a sliding layer, perimeter insulation with 60 mm thickness, and a clean layer with 5 cm thickness. The earth-filled WU basement exterior walls received perimeter insulation, 100 mm.
Now, the site manager and we have noticed that there are damp spots on some walls. At one spot, water slightly seeped in between the floor slab and the wall, creating a small puddle on the floor. At another spot, water penetrated the wall (photos attached). Fortunately, the site manager dealt with it immediately and is following up to "make sure everything is fine."
The spots have now each been generously injected by a company that supervised the execution of the [Weiße Wanne] (one spot about a month ago, the other about 2-3 months ago) and are now apparently "sealed." At one spot, water ran out of the wall during drilling; according to the employee's statement, he apparently had to drill through the "joint sheet"/the sealing (warning, layman) to ensure that everything is sealed.
During a renewed inspection of the construction site, we have now found new damp spots and are now uncertain "whether it is usual" that in a new building with [Weiße Wanne], that several injections must be done at different spots already at the beginning. Unfortunately, the basement is already completely filled in, and a "foil" (vapor barrier?) has already been laid inside the basement. The latter is "only" glued to the wall.
We have already informed the site manager about the renewed spots.
Has anyone had similar experiences? We are very grateful for any feedback.
we are currently in the process of building a house with a general contractor who is also "responsible" for the basement.
A solid house is being built, fully basemented with a [Weiße Wanne], whereby the basement, which consists of WU concrete, is completely "in the ground," i.e., not, for example, partially exposed. In the basement itself, there are waterproof light shafts in every room. The soil survey confirms no pressing groundwater.
The WU construction is/was carried out according to the contract as follows (excerpt only):
Approx. 24 cm thick reinforced concrete walls made of in-situ concrete, 30 cm thick reinforced concrete floor slab with reinforcement, PE foil as a sliding layer, perimeter insulation with 60 mm thickness, and a clean layer with 5 cm thickness. The earth-filled WU basement exterior walls received perimeter insulation, 100 mm.
Now, the site manager and we have noticed that there are damp spots on some walls. At one spot, water slightly seeped in between the floor slab and the wall, creating a small puddle on the floor. At another spot, water penetrated the wall (photos attached). Fortunately, the site manager dealt with it immediately and is following up to "make sure everything is fine."
The spots have now each been generously injected by a company that supervised the execution of the [Weiße Wanne] (one spot about a month ago, the other about 2-3 months ago) and are now apparently "sealed." At one spot, water ran out of the wall during drilling; according to the employee's statement, he apparently had to drill through the "joint sheet"/the sealing (warning, layman) to ensure that everything is sealed.
During a renewed inspection of the construction site, we have now found new damp spots and are now uncertain "whether it is usual" that in a new building with [Weiße Wanne], that several injections must be done at different spots already at the beginning. Unfortunately, the basement is already completely filled in, and a "foil" (vapor barrier?) has already been laid inside the basement. The latter is "only" glued to the wall.
We have already informed the site manager about the renewed spots.
Has anyone had similar experiences? We are very grateful for any feedback.