Bulla2000
2010-11-22 17:36:13
- #1
Hello, we are close to finalizing our contract for work according to the Building Code for the construction of a single-family house with DEURA (see the related topic here in the forum). According to their regulations, DEURA is liable for damages proven to have resulted from delays (e.g. interest costs, rent, canceled move etc.).
My construction supervisor would like to include a penalty clause according to which the company pays a certain amount per week of construction delay regardless of fault. The company rejects such a clause and refers to their contract (see above).
Our problem is that we do not live in rented accommodation and will not have any additional financing costs. A construction schedule will be contractually agreed upon. The only damage I currently see if we cannot move in as planned is the cost of travel for our daughter's school commute. She is to be enrolled near the construction area to avoid changing classes. For this, we have to drive her about 25 km each way every day. This would be the damage starting from the first day after the agreed completion date.
This damage is not very large, so it is hardly suitable as real leverage.
What would you recommend? On the one hand, I have little fear that there will be a construction delay because first, 8 months are planned and according to previous experience DEURA does not fall behind schedule, on the other hand, the existing regulations might be sufficient.
Is a solution like the above (penalty clause) common or should I not insist on it?
My construction supervisor would like to include a penalty clause according to which the company pays a certain amount per week of construction delay regardless of fault. The company rejects such a clause and refers to their contract (see above).
Our problem is that we do not live in rented accommodation and will not have any additional financing costs. A construction schedule will be contractually agreed upon. The only damage I currently see if we cannot move in as planned is the cost of travel for our daughter's school commute. She is to be enrolled near the construction area to avoid changing classes. For this, we have to drive her about 25 km each way every day. This would be the damage starting from the first day after the agreed completion date.
This damage is not very large, so it is hardly suitable as real leverage.
What would you recommend? On the one hand, I have little fear that there will be a construction delay because first, 8 months are planned and according to previous experience DEURA does not fall behind schedule, on the other hand, the existing regulations might be sufficient.
Is a solution like the above (penalty clause) common or should I not insist on it?