Good morning,

the windows were delivered yesterday. The window installer noticed that one window is 10 cm too narrow. He said it was his mistake; he can order a new one (probably takes another 14 days+) or install this one. On the left edge, he wants to put Styrodur in between, which insulates very well.

In principle, I do not want to wait that long again because all upcoming trades (electricity, gas, plumbing) will only start once ALL windows and doors are installed.

Is it safe to use Styrodur for this, or could cold bridges and thus mold develop? After all, it is also used to insulate all kinds of concrete parts.

The masonry is 36.5 Poroton stone. And it is a new building; the roof truss has just been completed.

Thank you
 

Ickes

2017-08-10 05:24:46
  • #2
I have now found the following after a longer Google search:

it is described: "...using Styrodur on the inside is tricky if it is not fully glued over the entire surface and without cavities. It is virtually vapor-tight and not capillary-active. Moisture condensed between the wall and Styrodur can lead to mold growth.

Better would be a thin calcium silicate board with a suitable system adhesive. Apart from that, reveal insulation is recommended."

Accordingly, the idea with Styrodur would be dangerous in my opinion, as moisture accumulates between Styrodur and the masonry, which can lead to mold.

So the question arises whether one should not build up the 10cm with Poroton bricks. Then you would have "one" wall and (from my point of view) moisture could not form since there would no longer be a warm/cold gradient?
 

kbt09

2017-08-10 06:30:41
  • #3
And how about ordering the window to size and meanwhile installing the wrong window temporarily?
 

Bieber0815

2017-08-10 06:34:08
  • #4
We received new windows in 1991 or so, and one was too small. A board was used as a temporary solution until the delivery and installation of the [passendes Fensters].
 

DNL

2017-08-10 06:55:13
  • #5
Two windows were damaged and therefore not installed. This took several weeks. For that long, OSB boards were simply installed there. Then the other trades are still protected.

And looking at the entire living period, two weeks is really nothing. Do you really want to make compromises because of that?
 

winnetou78

2017-08-10 06:58:36
  • #6
There are aerated concrete panels exactly 5 cm thick, each side one edge and done.
 

Similar topics
19.11.2013Walls made of Styrodur or Styrofoam?10
27.05.2015Huge problem with condensation on the window34
20.12.2019Trefz window prices and experiences?14
20.07.2015Moisture/Mold in the basement10
07.09.2015Kniestock height 2-story windows eaves side14
04.04.2016Drywall boards mold?57
09.09.2016Controlled residential ventilation and still open windows at night71
08.09.2016Window connection / reveal in double-leaf masonry24
05.12.2017Humidity in basement apartment71
28.05.2018Windows & window size: what to choose? Double-leaf windows?46
27.03.2019Moisture in the exterior wall of a 300-year-old house19
04.04.2023What is more expensive? Masonry or windows?21
18.10.2020Window & door installation not compliant with standards28
20.01.2021Moisture seeps through the floor-to-ceiling windows in the new building34
13.03.2021Moisture in the property30
27.05.2021How do I keep mold away from the attic?31
22.08.2021House renovation, year of construction 68, mold and co76
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49
22.08.2022Mold on uninsulated flat roof equipment room15
03.01.2025Does mold go away by insulation or not?18

Oben