netzplan
2019-08-18 22:26:34
- #1
Hello everyone,
our strip foundation for our double garage is already finished. Now the gravel is being worked on and afterwards the floor slab (probably 15cm) will be created.
The yard in front of the garage is about 8m from the street. The builder has so far laid the gravel so that the floor slab is about 10cm above street level. However, he recommends 15cm and therefore suggested another 5cm of screed or something similar so that we reach 15cm.
1. Question: Is screed actually suitable for a garage floor or should we raise the floor slab by 5cm and only install an industrial floor? According to the builder, the raw floor should not be left as is, because, for example, saltwater in winter would not be good for the floor.
2. Where is the position of an edge strip usually located at the garage entrance? For example, sectional door. Do you lay the floor (e.g., screed or industrial floor) rather up to the inner edge of the walls (garage entrance) and then lay the outer/paving stones slightly into the garage entrance (i.e. the wall thickness of the garage entrance)? If yes, then this would have to be taken into account when formwork for the floor slab is done.
Best regards
our strip foundation for our double garage is already finished. Now the gravel is being worked on and afterwards the floor slab (probably 15cm) will be created.
The yard in front of the garage is about 8m from the street. The builder has so far laid the gravel so that the floor slab is about 10cm above street level. However, he recommends 15cm and therefore suggested another 5cm of screed or something similar so that we reach 15cm.
1. Question: Is screed actually suitable for a garage floor or should we raise the floor slab by 5cm and only install an industrial floor? According to the builder, the raw floor should not be left as is, because, for example, saltwater in winter would not be good for the floor.
2. Where is the position of an edge strip usually located at the garage entrance? For example, sectional door. Do you lay the floor (e.g., screed or industrial floor) rather up to the inner edge of the walls (garage entrance) and then lay the outer/paving stones slightly into the garage entrance (i.e. the wall thickness of the garage entrance)? If yes, then this would have to be taken into account when formwork for the floor slab is done.
Best regards