Hi. I made a list of the ancillary construction costs. The connection costs for electricity and water I took from the local ordinance, sewage and internet I estimated.
Did I forget something, set it too low or too high? I would appreciate it if you could take a look. Building land would be [NDS]
Plot
land transfer tax (5.5%) 3520
notary fees 2500
land registry entry 1800
Construction preparation
surveying 2600
connection construction water 180
connection construction electricity 180
construction electricity costs 1500
construction water costs 500
fees for building permit, house number, etc. 1000
Insurances/Expert
builder liability insurance 180
fire shell insurance 170
expert 3500
Earthworks
soil analysis 1000
reserve soil replacement 4000
House connection
electricity 1600
water 1400
internet 1500
sewerage 2000
painting work 6000
floor coverings 4000
construction road 5000
44130
Did I forget something, set it too low or too high? I would appreciate it if you could take a look. Building land would be [NDS]
Plot
land transfer tax (5.5%) 3520
notary fees 2500
land registry entry 1800
Construction preparation
surveying 2600
connection construction water 180
connection construction electricity 180
construction electricity costs 1500
construction water costs 500
fees for building permit, house number, etc. 1000
Insurances/Expert
builder liability insurance 180
fire shell insurance 170
expert 3500
Earthworks
soil analysis 1000
reserve soil replacement 4000
House connection
electricity 1600
water 1400
internet 1500
sewerage 2000
painting work 6000
floor coverings 4000
construction road 5000
44130