We have only just applied for it now, and implementation is only possible from 23.1. Even then, the work will take up to 14 days. We expect the building permit to arrive any day now, and in about a week the earthworks should begin.
Everything here is part of the shell construction trade -> topic for the shell constructor.
Are you seriously planning to start the excavation this year? No concerns about frost / foundation slab?
Every morning I get the cold sh... when I see the weather and its forecast. We were actually told "excavation this week," but I no longer expect anything to happen this year. At least the batter boards are already set up [emoji6] Construction site: Middle Franconia... -> snow and below zero degrees next week, and nothing will probably happen from the week before Christmas until the end of week 1 anyway...