Hi everyone,

I am still quite inexperienced (book is on the way) and planning a timber frame house. Land is in sight.

At first, I only want to order a shell construction. The house has the following key data: - 12 by 8 meters - basement livable - timber frame - 1.5 floors, meaning ground floor plus upper floor

Since my budget will increase in 1.5 to 2 years, I want to commission the shell construction now. And then in 1.5-2 years the remaining trades. For this first house construction phase, I have 320k available.

Questions: 1. Which timber house providers specialize in shell construction? 2. Which trades (interior finishing, electrical, heating, etc.) are possible with 320k and which should I prioritize in the shell construction?

I look forward to all helpful ideas, experiences, tips.
 

11ant

2024-09-11 20:21:44
  • #2
Which book are you expecting to relieve your ignorance? - unfortunately the respondents to your main thread are still waiting for you to respond to their follow-up questions (or suggestions away from wooden construction). And we look forward to dialogues. 1. The desired completion level "closed shell" you don’t get only from wood. 2. Electrical and heating, but also water installation, you should already have done by others. Without construction water you won’t get any craftsmen.
 

-LotteS-

2024-09-11 20:39:41
  • #3


Well, you can also solve that with a standpipe and a proper hose. It cost us about 25 EUR rent per month, and 20 cubic meters are already included. Great piece – you just have to store it well, the deposit is a few hundred euros.

You can do the electrical work later if you have the empty conduits in the walls; plumbing can be surface-mounted in a pinch (if planned well, that's no drama). Installing the underfloor heating and water/sewage pipes would be the only things that absolutely must be done beforehand if the screed is already to be laid (assuming precise specialist planning of course – for that, you have to know exactly what, how, why, and maybe later where you want something...)
 

11ant

2024-09-11 21:00:33
  • #4
Why bother with temporary solutions when all the house entries are in and all meters can be installed? Water in the guest WC, electricity up to the cabinet. Of course, no bidet yet, no access points, etc.
 

-LotteS-

2024-09-11 23:04:05
  • #5
The scaffolding was in the way and the municipal utility’s excavator didn’t want to dig underneath - so it only happened much later than planned. We only had a 3m house entry, not 5m...
 

-LotteS-

2024-09-11 23:06:46
  • #6


... and they all came only after the screed was in. Before that, there would have been no appointments oO
 

Similar topics
27.02.2015Purchase shell construction and complete it including financing15
31.07.2016Electrical inspection, Q2, bathroom tiles, knee wall, floor-to-ceiling windows23
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
20.04.2017Payment plan with 35% after the shell construction, okay?10
07.10.2017From when must the shell construction be dry or sealed?16
09.01.2019Final invoice for shell construction (200 sqm, clinker, without basement, roof) ok?24
26.10.2020Kitchen measurement in shell construction mode13
01.05.2021Property with expansion house experiences14
07.06.2021Installation of heat pump/heating - before or after screed16
25.11.2021Getting rid of moisture from the shell construction - how to ventilate and other topics18
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49
23.02.2022Possible subsidies when replacing an old oil heating system?16
18.11.2022Heating not available - Who bears the costs?77
24.02.2023What kind of flooring in the utility room on screed - DIY, tiles?34
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57
24.02.2025Construction Costs Shell/Turnkey Comparison39
26.03.2025Construction costs for the shell structure - turnkey Kreis Wesel44

Oben