Marko958
2016-11-07 09:10:22
- #1
Good day,
I hope I have chosen the right subforum. Otherwise, it can be moved gladly. ;)
The shell is now up, the windows are in, and this week the roof will be covered. In two weeks, the partition walls (Gypsum board) will be installed.
Slowly the question of the house connections arises, and today the local energy supplier (Thüringen Energie) is coming to discuss details. The connection costs around 2000 € including civil engineering; with own civil engineering, 90 € will be reimbursed. Excavation of about 8-9 m is necessary.
Now to the question:
Our site manager from the main contractor advises us to have the civil engineering work for electricity done together with those for water and wastewater. Although the 90 € savings would not cover the costs, coordination would be easier.
The network operator says that he prefers to have the excavation done himself because when laying simultaneously with water/wastewater, a stepped trench must be created.
It is important to know that all connections are located at one point on the property.
How has this been done with you?
Many thanks
Marko
I hope I have chosen the right subforum. Otherwise, it can be moved gladly. ;)
The shell is now up, the windows are in, and this week the roof will be covered. In two weeks, the partition walls (Gypsum board) will be installed.
Slowly the question of the house connections arises, and today the local energy supplier (Thüringen Energie) is coming to discuss details. The connection costs around 2000 € including civil engineering; with own civil engineering, 90 € will be reimbursed. Excavation of about 8-9 m is necessary.
Now to the question:
Our site manager from the main contractor advises us to have the civil engineering work for electricity done together with those for water and wastewater. Although the 90 € savings would not cover the costs, coordination would be easier.
The network operator says that he prefers to have the excavation done himself because when laying simultaneously with water/wastewater, a stepped trench must be created.
It is important to know that all connections are located at one point on the property.
How has this been done with you?
Many thanks
Marko