I am still waiting for feedback from the GU. My current status is that we can start the painting work about 4 weeks after the screed, again with another 4 weeks.
I believe I was told 6 weeks for readiness for covering by the GU.
At Mebofix I found this info:
How quickly does a calcium sulfate screed dry at all?
Under normal building conditions, the drying time of a calcium sulfate screed can be determined using a simple formula:
"Thickness of the screed squared multiplied by the factor 1.6"
This relation, borrowed from concrete technology, results in a drying time of 6 x 6 x 1.6 = 57.6 days for a six-centimeter thick screed – that is almost two months!
What is done in the period between screed and moving in is, in my opinion, just "peanuts," or am I mistaken?
Set up technology for heating and ventilation
Water, pipes, lifting pump
Tiles
Steel stringer staircase
(House) doors
Complete electrical installation
Painting work
Laying the floor
Touch-ups