Renewed financial planning for the bank (buffer possible?)

  • Erstellt am 2018-03-06 16:57:11

flo_fluffy

2018-03-06 16:57:11
  • #1
Hello everyone,

my wife and I have just applied for a construction loan and have now received the approval *yippee*. Unfortunately, our bank finds the financing list (additional building costs, AA) quite high. My question is now, is it allowed to list a buffer of about 11k as a position? Or is that not very well regarded? Especially with the laying + excavation of the trench + closing of the water pipe / civil engineering, we are very uncertain and have calculated accordingly 'a lot'. I have now adjusted our financing plan, but I am still very unsure. Moreover, during construction, changes and possibly adjustments inevitably occur.

Construction costs are probably okay
283,465 €

Additional building costs
Drinking water connection 2,500 €
Rainwater connection 3,000 €
Wastewater connection 3,000 €
Electricity connection 2,500 €
Telephone connection 800 €
Soil investigation (for disposal) 600 €
Disposal and removal 2,000 €
Building surveying 650 €
Connection of construction electricity, water, heating
500 €
Buffer 8,824.53 €

Outdoor facilities
Garden own work 500 €
Driveway / parking space own work 4,000 €
Driveway material 4,000 €
Greening material 2,040 €
Fencing 1,800 €
Buffer 2,000 €

* own work

The construction itself is carried out with a developer in Bavaria, but without the installation of water, electricity, and telephone. A single (i.e., combined shaft) is needed on our property.

We would be very happy about a short assessment
 

ypg

2018-03-06 17:24:42
  • #2
But of course, you can name buffers of, for example, 10 or 15%.

However, I consider your calculation to be too low:
For the incidental construction costs, for example, the earthworks are missing. I know, these are included up to 30cm by the construction company, but that will be sufficient in 99% of cases. Even on level plots, that can easily be 10,000 euros.
Soil investigation report is missing, or does the builder pay for that?
Then standby interest can also occur... Roughly estimate 1,000 euros.
Surveying costs should also be 2 to 4 thousand.
Connection of construction power/water is okay, but what about rental and consumption costs?

The exterior landscaping also seems too low despite the EL - what about the drainage border for the house, which also costs, as well as the house pedestal...

Take a look here:
 

flo_fluffy

2018-03-06 19:26:05
  • #3
hi,
Excavation from the house and backfilling (approx. 15k) with stable material will be carried out by the developer and is already included in the house price. The soil survey was taken over as well, and the consumption costs for construction electricity and water (only the connection fees are not) are also covered by the developer. Surveying costs do not apply either since, fortunately, we purchased the plot from the municipality in a new development area.
We have not included the standby interest because it is not co-financed by the bank. We have not yet given any thought to the drainage surround, thank you very much for the hint. We will take a look at the link, it really seems to be detailed.
Thank you very much
 

ypg

2018-03-06 20:05:37
  • #4
... a plot of land from the municipality will also be surveyed for you. Well then: those were examples. Of course, the calculation also includes things that do not need to be financed. The bank does not want a partial calculation but wants to be able to assess the entire project. Also, be careful what is included for you. There are limits everywhere in the construction service description - the BU will not dig 3 meters for free ;)
 

Similar topics
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
11.10.2022List of incidental construction costs. More expensive "on the builder's side"?154
07.07.2014Develop the property yourself13
06.01.2015First buy the plot, then calmly plan and build...?11
16.02.2015Property purchased - Is financing/loan for house possible?13
31.03.2015Property / Financing amount / Insurance? Experiences10
13.06.2015New construction with developer / construction drawing documents23
16.10.2016Construction ancillary costs not visible?14
28.07.2017Calculation / Additional Costs Expansion House28
14.07.2017What is the maximum cost my property can have?21
27.02.2019Plot of land including turnkey house - experiences?46
06.01.2020House purchase, prefabricated house from the developer with land10
04.05.2020Assessment of land - hillside location15
18.10.2020Baunebenkosten calculation realistic?94
09.09.2020Calculation of a prefabricated house19
13.10.2020Land available - ancillary construction costs, ancillary house costs, financing?34
27.02.2021Prefabricated house including land planned - financing45
16.03.2022Additional construction costs when building a house with a developer88