Proof according to building regulations necessary, is the soil free of silt?

  • Erstellt am 2010-12-21 08:35:02

Krolock

2010-12-21 08:35:02
  • #1
Our general contractor (GU) was probably a bit offended because he was not allowed to bring his companies for the earthworks and house connection (15,000 euros more expensive) on board. This had consequences... Basically, the soil report states "backed-up seepage water," therefore sealing according to DIN 18195 Part 6. This should have been included in the GU's calculation since the report was already available at the time of the house offer. The soil expert recommended possibly a drainage system. However, the GU was of the opinion that sealing according to DIN 18195 Part 6 was sufficient and never let the drainage be offered through his companies. We awarded the contract externally, and the GU also gave our selected earthworks contractor a contract for excavation and backfilling.

We had some problems because the GU did not accept the excavation pit from the earthworks contractor. We had requested the earthworks contractor in writing to have the excavation pit accepted by the GU. But the earthworks contractor did not do this, and the GU simply started building the basement. Then I found clay in the excavation pit. Construction was stopped, and the soil expert had to give his OK. Now drainage is mandatory because there is clay and no soil replacement has taken place. Water accumulates in the foundation area.

As builders, we wanted to be on the safe side and additionally planned a drainage system at our own expense. The GU used this as an opportunity to unilaterally seal only according to DIN 18195 Part 4 (ground moisture) without consultation. Furthermore, he did not supervise the backfilling above the drainage. According to the construction service description: "Working spaces are backfilled with existing soil, provided it is suitable." Upon our written request whether the soil was suitable for backfilling at all, he refused to test the backfill material because he only pays the earthworks contractor for this service and we had selected him. :eek: How do you see this? Do we have a claim for sealing according to DIN 18195 Part 6? Can we demand proof from the GU that the soil (as required in the soil report) is free of silt? We cannot hold the earthworks contractor responsible since the order for backfilling and compaction came from the GU.
 

Similar topics
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
23.11.2014Soil report shocked us!!34
06.10.2015Correct formulation for a waterproof basement11
07.07.2025House Pictures Exchange - Show your house pictures!11887
16.12.2015Rain drainage with or without flushing shafts12
05.01.2016Drainage and flushing shaft in boundary construction12
24.08.2021Slope position, basement open at the front, bathtub31
11.10.2017Sealing on Styrodur insulation?14
21.04.2019Floor plan planning shortly before submitting the building application1420
10.07.2018Does the structural builder have to paint the transition between styrofoam and brick wall black?12
22.06.2018Unauthorized high-quality work - additional costs25
04.02.2020Installation of additional insulation for underfloor heating - cables lie on the raw floor slab25
25.02.2020What should we pay attention to in the soil report?21
15.02.2020Building waterproofing of earth-contacting components16
08.08.2020Foundation slab impossible without a soil expert?10
08.10.2024Drainage around the house, but how?17
20.12.2022Lowering of groundwater according to soil report - Your experiences?57
15.11.2023Berlin front structure for securing the excavation pit23
15.01.2024Interpretation of the soil survey report19
01.11.2024Danwood complete offer vs. separate commissioning architect13

Oben