Rollo1512
2016-12-18 12:57:56
- #1
Hello,
my fiancée and I are planning to buy and develop a plot of land. It is a newly released area that has been divided into 3 plots. My best friend is interested in the neighboring plot and we have also met the third party and get along well...
Our plot measures 770 sqm, my friend's 450 sqm, and the third party's 650 sqm.
One downside of the plot is the private road that needs to be developed.
1. We are supposed to pay for the land under the road as building land (after all 370 EUR/sqm) - is that normal?
2. We have to remove a hill that lies on the access road (a soil report is available) - cost for development and removal about 80,000 + VAT and additionally 75,000 for the land. That would be about 160,000 EUR just for the road.
3. How is the road cost calculated? Divided equally by 3 or depending on the plot size?
It would be nice if you could help.
Best regards and Merry Christmas!
my fiancée and I are planning to buy and develop a plot of land. It is a newly released area that has been divided into 3 plots. My best friend is interested in the neighboring plot and we have also met the third party and get along well...
Our plot measures 770 sqm, my friend's 450 sqm, and the third party's 650 sqm.
One downside of the plot is the private road that needs to be developed.
1. We are supposed to pay for the land under the road as building land (after all 370 EUR/sqm) - is that normal?
2. We have to remove a hill that lies on the access road (a soil report is available) - cost for development and removal about 80,000 + VAT and additionally 75,000 for the land. That would be about 160,000 EUR just for the road.
3. How is the road cost calculated? Divided equally by 3 or depending on the plot size?
It would be nice if you could help.
Best regards and Merry Christmas!