Principal's Guarantee

  • Erstellt am 2012-02-26 18:46:27

Projekt 2012

2012-02-26 18:46:27
  • #1
Hello everyone,

Over the past few weeks, I have read thoroughly through this forum and was impressed by the many helpful tips and information!! That is why I registered here today to participate in the discussions and exchange of experiences!!

I am also planning to build a prefabricated house and have already had some contact with consultants from various companies... One consultant informed me that his company generally requires a financing confirmation with a guarantee certificate from the bank of the builder covering at least 70% of the contract sum! Thanks to the posts here in the forum, I was at least sensitized to this issue and possible risks (e.g., payments despite defects or services not rendered) and would like to find out,

a) whether the clauses mentioned below are among those that are advised against
b) whether such clauses are now standard (after the relevant Federal Court of Justice ruling)
c) or whether I should be "concerned" about having been with the "right construction company"

For example, the guarantee certificate states among other things:

"Builder instructs bank to transfer to construction company according to the following payment schedule (percentages according to construction progress follow)"

"Builder's bank assumes the suretyship for all payment obligations incumbent on the builder as a primary debtor, waiving the objection of prior enforcement..."

"Bank of the builder waives the objection of contestability and set-off, provided the builder’s right of contestation / counterclaim is neither undisputed nor legally established..."

What is to be made of this? Are such formulations common? Is this an assignment of claims??

Thanks for your opinions!!!

Regards

"the Newcomer"

Project 2012
 

Bauexperte

2012-02-26 19:30:27
  • #2
Hello,



(...)


Yes, that could be called that and with that the point "c" should answer itself.

Serious companies expect from you a financing confirmation with the note that these confirmed funds may only be used for the house construction. Companies set up in this way generally offer you in return a completion guarantee, which after the end of the construction period turns into a 5-year warranty guarantee.

Interesting in this context would be the amount of installment payments to be made until the closed shell in percent. I am almost certain that the amount will evolve implicitly according to the conditions you mentioned regarding the guarantee document.

Kind regards
 

Projekt 2012

2012-02-26 20:26:08
  • #3
Hello construction expert!

Thank you for the quick response! Hm...I don't know if one is allowed or should mention names here, but I actually considered this company to be very reputable and working in the higher price segment...or at least I have heard and read corresponding positive things...

Regarding the payment terms in the guarantee:

10% after production-technical inspection and return of the production plans to the architect

70% after the building structure is erected, windows, shutters, chimney, front door installed, roof covered, sanitary and electrical installations executed

15% after plaster surfaces are filled, bathroom complete/bathtub installed

5% remaining amount after submission of the signed acceptance protocol

Regards and have a nice evening

Project 2012
 

Bauexperte

2012-02-27 11:59:21
  • #4
Hello,


Why shouldn't you be allowed to? Many users here ask about the experiences of other users with the providers "xyz"; you should only refrain from advertising (i.e. linking).


So after submission of the permit-free building approval; that is okay.


In one sum or in how many payment installments?

Kind regards
 

Projekt 2012

2012-02-27 13:19:12
  • #5
Hello construction expert,

the 70% is requested as a "lump sum" after completion of the mentioned works (timed on the 4th day of construction), so no further partial payment steps between the already paid 10% in step 1 and this partial installment....

Regards

Project 2012
 

Bauexperte

2012-02-27 20:40:15
  • #6
Hello,


That means your prefabricated house comes literally finished, electrical installation completed and sanitary rough installation ... interior doors, windows, etc.?

Hmm - is there an acceptance inspection before you have to pay the 70%?

I rarely or never deal with such constructs and am accordingly curious; still also regarding the provider

Kind regards
 

Similar topics
27.02.2015Burglary-proof windows?33
03.06.2014Interior design - windows14
16.01.2018Is an extra charge for colored windows realistic?19
18.06.2014Inspector defect identification, determination of window installation10
18.05.2016Help needed with window arrangement!32
27.05.2015Huge problem with condensation on the window34
20.12.2019Trefz window prices and experiences?14
26.01.2015Window between two rooms13
13.03.2015Opinions on window parapet height sought30
09.04.2015For porthole, special regulations? Window, single-family house 1.5 stories.18
22.04.2015Window, roller shutter, exterior plaster10
28.05.2015Round window - dissatisfied with the interior reveal16
27.05.2015Which roller shutters with a closed window, only glazing?13
15.10.2015Kitchen planning with deep windows43
16.09.2019Windows in new buildings: triple glazing with a green tint?21
26.06.2015Floor plan question, stairs, window, orientation12
07.09.2015Kniestock height 2-story windows eaves side14
25.03.2017From when is the financing confirmation legally binding for the bank?33
05.07.2019Funding confirmation or how to spend more money...35
22.03.2023Financing confirmation for equity14

Oben