R.Hotzenplotz
2018-05-07 10:10:38
- #1
Actually, only the stressed client remains, who writes emails on weekends and threatens to stop the concreting
I am not threatening. I only stated that without approval the concreting cannot take place. But that has since been granted.
Regarding the missing coordination and delay, apologies were also made. The culprit is now the shell builder, who repeatedly failed to keep commitments. The general contractor even called the suppliers to check whether the shell builder had actually ordered the Poroton bricks, whether they would deliver them, etc. (liquidity). But they are supposedly also scheduled to arrive today. Because without Poroton it will be difficult to complete the upper floor within five working days, which is supposed to be finished by Saturday.
All in all, things went poorly and it is certainly still a coordination problem. But now it is also resolved.