R.Hotzenplotz
2018-05-06 12:05:15
- #1
Hi!
We are building with a general contractor and have separated out the electrical trade because the general contractor's electrician does not offer KNX.
So far so good.
The general contractor's site manager was unable to arrange an appointment with the electrician to lay pipes in the ground floor ceiling before the concrete slab was poured. They then agreed by phone that the electrician would simply drill through the ceiling into the Halox boxes. The site manager indicated he saw no problem with this.
However, he has so far failed to provide the written approval requested by the electrician for the drilling process. The ceiling is supposed to be concreted tomorrow morning. Unfortunately, I only just learned from the electrician that the written approval is not yet available. He indicated to me that he will not perform any drilling without such approval. It is too risky for me to allow the concreting to proceed tomorrow without written approval. A verbal agreement with the electrician or with me is not worth anything in this case.
Now my question:
How should it be viewed if Halox boxes are drilled through in the concrete ceiling? Is it risky? Is it correct for the electrician to want this approval in writing? I think this is reasonable on his part.
How would you proceed here? If they pour the concrete tomorrow and still do not provide approval, I will be the one at fault later! I have just emailed the general contractor again, stating that written approval must definitely be provided before the concreting begins and otherwise no concreting can take place. Whether this will help on a Sunday, given that the work is supposed to begin at 8 a.m. tomorrow, is a big question. On the other hand, the shell builder who is supposed to carry out the work tomorrow is not my contracting partner and legally I can hardly prevent him from starting work at 8 a.m. (contract for work and services). At least in legal terms such as potential damages for reserved manpower, machinery, etc., I do not know how this would affect things.
Does anyone have an idea how I should best proceed here?
In any case, I need to get more involved in all the processes, follow up much more, get much more and also more short-term written confirmations. It started off quite well but now 2-3 such things have already occurred.... (among other things we had an "experience" during the civil engineering work and the related coordination/communication).
We are building with a general contractor and have separated out the electrical trade because the general contractor's electrician does not offer KNX.
So far so good.
The general contractor's site manager was unable to arrange an appointment with the electrician to lay pipes in the ground floor ceiling before the concrete slab was poured. They then agreed by phone that the electrician would simply drill through the ceiling into the Halox boxes. The site manager indicated he saw no problem with this.
However, he has so far failed to provide the written approval requested by the electrician for the drilling process. The ceiling is supposed to be concreted tomorrow morning. Unfortunately, I only just learned from the electrician that the written approval is not yet available. He indicated to me that he will not perform any drilling without such approval. It is too risky for me to allow the concreting to proceed tomorrow without written approval. A verbal agreement with the electrician or with me is not worth anything in this case.
Now my question:
How should it be viewed if Halox boxes are drilled through in the concrete ceiling? Is it risky? Is it correct for the electrician to want this approval in writing? I think this is reasonable on his part.
How would you proceed here? If they pour the concrete tomorrow and still do not provide approval, I will be the one at fault later! I have just emailed the general contractor again, stating that written approval must definitely be provided before the concreting begins and otherwise no concreting can take place. Whether this will help on a Sunday, given that the work is supposed to begin at 8 a.m. tomorrow, is a big question. On the other hand, the shell builder who is supposed to carry out the work tomorrow is not my contracting partner and legally I can hardly prevent him from starting work at 8 a.m. (contract for work and services). At least in legal terms such as potential damages for reserved manpower, machinery, etc., I do not know how this would affect things.
Does anyone have an idea how I should best proceed here?
In any case, I need to get more involved in all the processes, follow up much more, get much more and also more short-term written confirmations. It started off quite well but now 2-3 such things have already occurred.... (among other things we had an "experience" during the civil engineering work and the related coordination/communication).