grericht
2020-11-18 21:35:20
- #1
I hope I am in the right section here. Our house is nearing completion. Now I have 2 questions. We pay everything according to the construction progress to the house construction company, according to previously agreed installments.
- [*
- At the beginning/mid-June, our basement walls and basement ceiling were poured. The invoice was issued with a service date of June even though the supports for the basement ceiling remained in place into July and a drying time of at least 28 days is assumed. [LIST=1] [*]Could one also count on acceptance of an invoice with a service date of 06/07/2020 here and could the lower VAT rate be applied? The underlying question is when concrete is considered "performed." After drying or when it comes out of the mixer? If completion is assumed after drying, then July would indeed be included. [*]Is it legitimate to remove the formwork just 16 hours after pouring the concrete for the basement walls and then place the filigree ceiling on supports 24 hours later (i.e., after 40 hours) and pour the ceiling again another 24 hours later (i.e., about 64 hours after pouring the walls)? I have not noticed any defects but I am not an expert and the house construction company apparently did not care, because they always work together with the shell builder and presumably do not criticize each other's work. I am also satisfied with the speed but of course want everything to proceed properly and I only might not see the defects because there is insulation and backfilling on the outside and plaster on the inside.