Payment plan suspicious

  • Erstellt am 2016-02-19 18:15:13

Payday

2016-02-22 20:44:49
  • #1
I find it much more gruesome that after laying the screed, only 6% is still missing. Very expensive parts come in between the screed drying and the house completion. And a lot of time passes with fast construction companies during the whole process (if construction takes 4 months, 4-6 weeks of drying is 1/3 of the time, during which you have basically paid everything but have not yet had everything installed in the house).

15% for aligning and 15% for putting up a few roof tiles is definitely too much! Here, 10% needs to be removed and at least added behind the screed drying (for example, tiling work finished). As already mentioned, windows are missing, which absolutely need to be included in the payment plan.

Everyone always insists on the last payment. It has to be paid suddenly right before handover (definitely before moving in). Otherwise, there are no keys :) The last payment is hardly any leverage, even if everyone likes to see it that way beforehand. You also have to look at how much these 3% are in actual euros. For really serious defects, the last pennies don't matter to the construction companies; for minor issues, they do anyway. Much more important than the 3% or negotiated 5% at the end is that you never pay (much) more than what you have already received. 65% after the shell construction is already quite harsh, but 6% still open after laying the screed is really not acceptable at all.

P.S.: The financing bank can also reject payment plans or cause the financing to collapse. The payment plan must be submitted for the financing.
 

infinite_sea_83

2016-02-23 19:52:56
  • #2
Thank you very much for your advice. I was able to renegotiate the payment plan. Now we pay exactly 55% after the shell is closed (even including windows :)). For the negotiation, I proposed a payment plan suggestion from Bauexperte from another post. Many thanks also at this point to Bauexperte for the tips.
 

Watcher78

2016-02-23 19:58:09
  • #3
Can you post the payment plan here? Thanks in advance.
 

Similar topics
26.09.2013What do you think of this payment plan?, Property appraisal18
26.02.2016Renegotiation of payment plan, please help25
31.07.2016Electrical inspection, Q2, bathroom tiles, knee wall, floor-to-ceiling windows23
01.08.2017Questions about the payment plan10
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
29.11.2016Front door only burglary protection / better materials - plaster, screed?10
05.01.2017Bathtub in front of the window - parapet height?14
22.03.2017Is a high first installment common in a payment plan?23
17.07.2017Payment plan okay - 13% after the floor slab?21
07.10.2017From when must the shell construction be dry or sealed?16
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
09.01.2019Final invoice for shell construction (200 sqm, clinker, without basement, roof) ok?24
29.11.2020Accept payment plan despite legal defects?12
07.05.2019Payment plan - unreliable? Your assessment11
20.02.2020Is the payment plan okay?10
04.05.2020Payment plan is somewhat okay or clearly optimizable37
11.12.2020Payment plan and unpleasant feeling11
25.11.2021Getting rid of moisture from the shell construction - how to ventilate and other topics18
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17

Oben