Once again a payment plan

  • Erstellt am 2013-01-14 20:15:00

TUNK

2013-01-14 20:15:00
  • #1
Hello,

I am currently planning my new own four walls.
At the moment, I have an appealing offer from a GÜ. So far, this company has made a very good impression and is also willing to accommodate change requests in the contract.
I have been thinking for a long time about how to adjust the payment plan so that it is fair for all parties.

This is how it stands in the current offer:

The following payment plan applies:
2.0% after completion of the building application or building notice
11.5% after completion of building drainage, base/foundation
13.0% after completion of the exterior walls and interior walls on the ground floor without cladding
12.0% after erection of the roof truss
9.0% after completion of roofing and plumbing work
9.0% after completion of cladding without window sills
3.5% after installation of windows and exterior doors
(without sealing and fine adjustment)
5.0% after completion of drywall rough installation
5.0% after completion of electrical rough installation
5.5% after completion of plastering
4.5% after completion of heating rough installation
4.5% after completion of drywall
4.5% after laying of screed
2.0% after installation of interior doors
2.0% after completion of heating and sanitary installation
2.0% after completion of electrical installation
5.0% after defect-free handover to the AG

A short info about the construction:

Detached single-family house approx. 190 sqm living area. Plus double garage or cellar
Solid construction and brick veneer
Kfw55 efficiency house
Rather upscale fittings

The following points give me headaches based on experience:

In response to an inquiry about how high the credit for the entire electrical work would be, I was told that the GÜ has costs of about €8,000 gross for it. In the payment plan, I pay significantly more for electrical work.

2% for completion of heating... from my point of view is far too little. The heat pump and the deep drilling alone should exceed this amount.

Now I hope for suggestions on which levers I should/can still turn. My wish would also be to have a final installment of at least 10%.

Thank you very much in advance.
 

Micha&Dany

2013-01-15 11:27:50
  • #2
Hello Tunk

I can't imagine that any (serious) provider would agree to a final installment of 10%. That is quite a lot of money...

Otherwise, I find the payment plan very detailed. In my (not very conclusive) assessment, it is also quite good. For example, you have paid 60% upon completion of the shell construction. That should be okay.

But other users here can certainly tell you more precisely

Best regards
Micha
 

TUNK

2013-01-15 14:15:37
  • #3
Hello Micha,

thank you for your answer.
That I counted 60% at completion of the shell construction, I have already noted positively. But as an example:
When the screed is in, I still have 11% of the total amount outstanding and no tiles, no painting, no heating (heat pump with deep drilling), no sockets, etc.
I do not believe that the construction company is still in advance at that point.

Therefore, I hope for help to narrow down the point from when I am approximately in advance.
 

vokono

2013-01-15 20:53:22
  • #4
Hello, is the probe drilling for the heat pump included in the total 6.5% for heating/sanitary? In our case, this was not the case due to uncertainties regarding the soil conditions. An €8000 credit for electrical work is too little for a house of this size. Especially with upscale equipment. Our [Gü] accommodated us there. Since I carried this out myself and justified it by saying that I would install it at a higher standard anyway (partly EIB installation, more sockets than specified in the [BB], etc.)
 

TUNK

2013-01-15 22:08:37
  • #5
Hello pre-consultation,

yes, the 6.5% includes everything related to heating and sanitation.
For the electrical trade, I kept the standard, hence the €8,000. I will probably remove the trade and contract an electrician I trust with the KNX installation.
That is why I didn’t even start to ask for surcharges for any additional electrical work.

My idea so far was to reduce the 2nd to 4th installment to 10% each in order to then apply slightly higher installments towards the end.
 

vokono

2013-01-15 22:30:16
  • #6
I don't understand the reason for the postponement. Does it have something to do with the financing?
 

Similar topics
19.05.2021Experiences with brine heat pump491
08.12.2015Payment plan: paid too much at the beginning?11
26.02.2016Renegotiation of payment plan, please help25
01.08.2017Questions about the payment plan10
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
28.02.2017Are securities customary for completion and warranty?24
17.07.2017Payment plan okay - 13% after the floor slab?21
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
14.09.2018Heating (Heat Pump) Incorrect, heat output too high?14
30.09.2018Payment Plan for Prefabricated House - Reviews and Experiences Desired10
07.05.2019Payment plan - unreliable? Your assessment11
14.12.2020Ice formation brine pipe heat pump78
11.12.2020Payment plan and unpleasant feeling11
07.06.2021Installation of heat pump/heating - before or after screed16
05.07.2022Renew old heating with heat pump or gas boiler and domestic hot water heat pump58
17.10.2022Heating screed with device vs. with heat pump: costs?19
18.11.2022Heating not available - Who bears the costs?77
02.03.2023Heat pump for KfW55 house 148 sqm99
07.10.2023How to plan heating with a heat pump in new construction?14

Oben