Exilpfälzer
2014-03-14 16:09:50
- #1
Hello,
in my new build I am in a very unpleasant situation. The shell is finished, windows and front door are installed, water pipe installation is done and the electrician was also finished so far. Now the plasterer was supposed to come and plaster the interior. It was agreed that I would plaster all the chases myself in KW8, and in KW9 the plasterer would start with the interior plaster. During this work, I first noticed on the ground floor that in the areas where the electrician made the chases in the 11.5 cm walls, the bricks of the top row had come loose. I then informed the construction company, whereupon the boss came with his foreman and concluded that the electrician had hammered the bricks loose with his Hilti. Furthermore, if the plasterer puts his plaster on it, they will hold. Later, the electrician gave me to understand by phone that the bricks were already loose beforehand; a second man had to hold the brick so that he could hammer in his chase. Well, I thought, whatever, it's only three bricks. I then knocked narrow chases in and filled them with mortar. Bricks firm, all good. When I got to my work on the upper floor, there was again a sad spectacle with the 11.5 cm walls. Here the situation is worse. It was not only the bricks in the chase areas that were loose but also the first and second neighboring bricks. However, as there is a wooden beam ceiling on the upper floor and no concrete ceiling, I was able to lift the bricks and found that the adhesive on the underside of the top bricks was practically non-existent. My layman’s suspicion is that the adhesive had already set when the last row was laid. It is likely that the cause in the ground floor is similar. It is noticeable that on one side of the wall no adhesive is visible in the joints, while on the other side the adhesive has actually run out.
So, the unpleasant thing about the situation is that both the electrician and the construction company are blaming each other. Neither was or is willing to take responsibility for this botch job. The architect says the masonry should have held. An expert says without inspection that the electrician only uncovered the botch. The cause was the carelessness of the construction company. However, the electrician is obliged to report this defect and stop his work so that the construction company can repair it.
So both are to blame for this mess.
The plasterer said: "If I can’t start in KW9, I will go to the next construction site and can only start with you in 4 weeks." But it is possible to embed mesh in the affected areas, which gives the plaster additional stability. So good, said and done. The additional costs are €750.00 net, which I do not want to bear.
My question is ultimately, are there and if so which VOB guidelines apply in such a case that help to convince the two affected craft companies to cover the additional costs and thus fulfill their warranty obligations?
Thank you.

in my new build I am in a very unpleasant situation. The shell is finished, windows and front door are installed, water pipe installation is done and the electrician was also finished so far. Now the plasterer was supposed to come and plaster the interior. It was agreed that I would plaster all the chases myself in KW8, and in KW9 the plasterer would start with the interior plaster. During this work, I first noticed on the ground floor that in the areas where the electrician made the chases in the 11.5 cm walls, the bricks of the top row had come loose. I then informed the construction company, whereupon the boss came with his foreman and concluded that the electrician had hammered the bricks loose with his Hilti. Furthermore, if the plasterer puts his plaster on it, they will hold. Later, the electrician gave me to understand by phone that the bricks were already loose beforehand; a second man had to hold the brick so that he could hammer in his chase. Well, I thought, whatever, it's only three bricks. I then knocked narrow chases in and filled them with mortar. Bricks firm, all good. When I got to my work on the upper floor, there was again a sad spectacle with the 11.5 cm walls. Here the situation is worse. It was not only the bricks in the chase areas that were loose but also the first and second neighboring bricks. However, as there is a wooden beam ceiling on the upper floor and no concrete ceiling, I was able to lift the bricks and found that the adhesive on the underside of the top bricks was practically non-existent. My layman’s suspicion is that the adhesive had already set when the last row was laid. It is likely that the cause in the ground floor is similar. It is noticeable that on one side of the wall no adhesive is visible in the joints, while on the other side the adhesive has actually run out.
So, the unpleasant thing about the situation is that both the electrician and the construction company are blaming each other. Neither was or is willing to take responsibility for this botch job. The architect says the masonry should have held. An expert says without inspection that the electrician only uncovered the botch. The cause was the carelessness of the construction company. However, the electrician is obliged to report this defect and stop his work so that the construction company can repair it.
So both are to blame for this mess.
The plasterer said: "If I can’t start in KW9, I will go to the next construction site and can only start with you in 4 weeks." But it is possible to embed mesh in the affected areas, which gives the plaster additional stability. So good, said and done. The additional costs are €750.00 net, which I do not want to bear.
My question is ultimately, are there and if so which VOB guidelines apply in such a case that help to convince the two affected craft companies to cover the additional costs and thus fulfill their warranty obligations?
Thank you.