Is it possible to prefer external financing (retrospectively) over equity?

  • Erstellt am 2020-06-21 20:37:04

Musketier

2020-06-22 10:01:45
  • #1

I don't know what the conditions are now, but for me in 2013/2014 the commitment interest rate was also higher than the loan interest rate.
I then also drew the KFW loan first because I had the largest interest rate differential to the commitment interest rate there.
Except for advance payments, the bank would be quite stupid to agree to a request for early disbursement if it is regulated differently in the contract.


It depends on the contract. In our case, a fixed repayment start was agreed upon and the first regular installments had already been paid, even though for various reasons only the shell was standing at the time and we had paid most of it from equity until then. Until the last drawdown, it was almost another three quarters of a year.
 

K1300S

2020-06-22 14:36:29
  • #2


How can it be that the commitment interest is then higher than the agreed nominal interest rate? I mean: does the bank also pay more interest for providing money than when it actually disburses the money? And couldn't the bank then – like the borrower – simply "draw everything at once"? Or are there laws that prohibit them from doing so?
 

Altai

2020-06-22 15:21:19
  • #3
As far as I know, the commitment interest rate has been the same for most banks since forever. For my financing in 2018 and one I know from 2006, it was exactly 3.0% (different banks). Only the loan interest rates were significantly higher in 2006 and lower in 2018. This is not an answer to the question why... just the impression that this number simply was not adjusted. However, I have occasionally seen offers with, for example, 1.8% commitment interest in the meantime.

By the way, in my case, interest on drawn amounts was due on a daily basis and repayment started one month after full disbursement. And from day x onward, commitment interest was also due.
 

K1300S

2020-06-22 15:28:32
  • #4
That is completely clear to me, but points out that the commitment interest also depends on the costs for the bank itself.

Until now, I also thought that the banks were simply charging a little extra for not drawing down, but perhaps that really isn't true.
 

HilfeHilfe

2020-06-22 16:26:07
  • #5
Such flexibility just costs.
 

K1300S

2020-06-22 16:30:30
  • #6
But that was not the argument from . And honestly, I don't see any increased flexibility there for me as a borrower. I would have more flexibility if I received the money credited to my account and could then directly dispose of it myself. (Yes, I know the bank won't do that, but I still have the impression that this is an outdated practice that should really be cut off as soon as possible.)
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
28.06.2013Construction financing / fixed nominal interest rate / commitment interest15
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
15.02.2022Provision interest - loan amount24
01.07.2023Provision interest and deadlines of the house building company in the work contract13

Oben