2012-05-03 16:22:40
- #1
Hello everyone,
I have a question regarding house connections.
We will soon start building a single-family house without a basement with a developer.
Now, according to the site manager, I am supposed to take care of the utility providers. I have now learned that individual institutions are responsible for gas (A), electricity (B), and water (C).
I have now seen that A also offers the multi-utility house connection. I am now getting an offer for this. I still need to get offers from B and C as well. B offers a "worry-free" package, meaning the line is laid without any own contribution.
Now to my question, how do I coordinate so that all of them lay their lines roughly at the same time (Telekom is also coming), without them having to keep opening and closing the supply trench?
:confused:
Thank you very much and best regards
Ingo
I have a question regarding house connections.
We will soon start building a single-family house without a basement with a developer.
Now, according to the site manager, I am supposed to take care of the utility providers. I have now learned that individual institutions are responsible for gas (A), electricity (B), and water (C).
I have now seen that A also offers the multi-utility house connection. I am now getting an offer for this. I still need to get offers from B and C as well. B offers a "worry-free" package, meaning the line is laid without any own contribution.
Now to my question, how do I coordinate so that all of them lay their lines roughly at the same time (Telekom is also coming), without them having to keep opening and closing the supply trench?
:confused:
Thank you very much and best regards
Ingo