We have found a plot of land suitable for us, which we will buy soon to build a single-family house on it.
We are unsure about the house connection costs or private development costs that will come our way. It appears that our plot 4 (see drawing) is located at the end of the private road. Plots 1-3 will also be newly developed with houses, single-family and semi-detached houses.
Currently, there is an old house on the plot at the boundary between plots 3 and 4 which will be demolished. This old house is supplied via the private road from the street (gas, electricity, water, cable). The lines are probably from the 1970s.
It is planned to completely renew these lines in one go and to set a connection branch for each of the adjacent houses. The costs would be divided equally among the neighbors, each paying one quarter.
How high would you estimate the total costs? Maybe someone has already solved something similar and can share their experience here.
Thank you very much for your answers
Carsten

we have been reading along with great interest for some time now and have already learned a lot.
Thank you for that!
We have found a plot of land suitable for us, which we will buy soon to build a single-family house on it.
We are unsure about the house connection costs or private development costs that will come our way. It appears that our plot 4 (see drawing) is located at the end of the private road. Plots 1-3 will also be newly developed with houses, single-family and semi-detached houses.
Currently, there is an old house on the plot at the boundary between plots 3 and 4 which will be demolished. This old house is supplied via the private road from the street (gas, electricity, water, cable). The lines are probably from the 1970s.
It is planned to completely renew these lines in one go and to set a connection branch for each of the adjacent houses. The costs would be divided equally among the neighbors, each paying one quarter.
How high would you estimate the total costs? Maybe someone has already solved something similar and can share their experience here.