Horizontal sealing of the base slab

  • Erstellt am 2017-01-26 20:54:15

KlaRa

2017-01-29 10:51:54
  • #1
@ "joho78": That is a very good decision! Because if a horizontal damp proof course was installed below or between the masonry units (this is not only necessary for ground-contacting floor slabs), it also shows that the planner assumed rising damp and wants to prevent the moisture from affecting the wall surfaces capillarily through this measure. I am not a lawyer, but in "case of emergency" (let us hope it will not occur and that the architect – as far as our concerns are justified – will be open to correcting his planning) you may have more than just a good position through this documentation and approach! --------------------------- I personally wish you success in your steps!! Regards: KlaRa
 

joho78

2017-01-29 19:00:38
  • #2
Thank you KlaRa!

Now I would just like to briefly ask one final question

If I can no longer manage the flame-bitumen variant, then the spray variant is probably the better option, compared to not applying any sealing at all, right? A several millimeters thick layer is applied after all, which has a sealing effect, correct?

Best regards and have a nice Sunday!
 

KlaRa

2017-01-30 09:05:40
  • #3
Hello "joho78". You pointed out in your initial question from January 26, 2017 (quote: "Installers and electricians are currently busy") that at the moment all installation lines are probably already laid and fixed on the raw ceiling. This means that bonding a bituminous surface waterproofing (flaming is only done on the roof) will no longer be possible. For this, a continuously shot-blasted, dust-free by suction and bitumen pre-primed concrete surface is required. These preparations are also needed for a liquid waterproofing. However, these are not standardized and must therefore be classified as special constructions (except bitumen thick coatings, but these are only approved for exterior surfaces) and must be coordinated and approved with the building owner before processing. The planner cannot or must not just apply these on their own! -------------------- The "spray variant," as you call it, is therefore also not usable. Especially since in the described initial situation a thickness check and continuous application (to ensure functionality and tightness) cannot take place at all and cannot be checked either. Such an execution would thus contravene professional rules; you should avoid prescribing or even accepting such a variant!!! What is still acceptable as a functioning emergency solution with installed installations (certainly no honor for the planner) I have already described: Surface waterproofing as sheet material, vapor-tight bonded in the overlapping joints, connection to the horizontal barrier of the wall surfaces. The visual chaos that results after completion of the installation can only be evened out with a bound, water-free filling. On this as a continuous plane, the thermal insulation boards in the calculated necessary thickness, on top PE foil as penetration protection against the mixing water of the wet screed, and on top the 45mm thick screed as standard screed (or at least 60mm as heated screed) are laid. This way, the situation can be controlled as a functioning execution. ------------------------------------ Note: These explanations are not legally binding advice, as I have only taken the local situation from the description. Good luck: KlaRa
 

joho78

2017-01-30 11:07:41
  • #4
Hello KlaRa!

Thank you for the detailed description. I have one quick technical question regarding "surface sealing as sheet material": Since the installations have now been completed and fixed to the floor, is this laid over and glued to the pipes? Shouldn't there be a filling underneath (I understand the need for one on top)? Otherwise, wouldn't a "space" form under these sheets?

Best regards
 

KlaRa

2017-01-30 11:22:07
  • #5
The membrane sealing is not a stretch film. It can largely follow the unevenness. A filling under the sealing is certainly possible; there is nothing against it. The disadvantage of this design is that the leveling layer/filling must be walked on again afterwards for the installation of the sealing. Unfortunately, this is often done without much care. As a result, uncontrolled footprints usually form by the executing workers, creating indentations in the already leveled filling. Once the sealing is installed above, this level can no longer be accessed for corrections. Smaller indentations should actually not occur, but with reference to the flatness standard DIN 18202 Table 3 Line 2 (for raw ceilings, on which the insulation elements are usually laid), this is rather uncritical. Because ultimately, the thermal insulation and also the screed (the latter due to its thickness) sufficiently and completely uncritically bridge these potential unevennesses. None of this is so decisive as long as the thermal insulation is above the sealing level! So: I have seen both variants, filling above and filling below (with regard to membrane sealing), in practice, and both work. One with somewhat more effort, the other with somewhat less effort.
-------------------
Regards: KlaRa
 

Knallkörper

2017-01-30 15:35:28
  • #6
How do you assess the influence of a possible membrane under the base slab (cleaning layer) on the necessity of a horizontal sealing above the base slab? Minor, moderate, or non-existent?
 

Similar topics
08.05.2014Most moisture from screed?25
20.07.2015Moisture/Mold in the basement10
05.12.2017Humidity in basement apartment71
18.01.2018Floor structure and substructure in the attic with filling?20
30.04.2018New construction - Is it advisable to lay basement tiles immediately? (Moisture)14
03.11.2018Moisture in the bedroom on the exterior wall - Where does it come from?10
06.03.2019Pouring in screed insulation, yes or no?11
27.03.2019Moisture in the exterior wall of a 300-year-old house19
04.07.2022Moisture on the house wall outside and inside21
26.02.2020Convert loose fill into bound fill using wallpaper paste?28
18.07.2020TGA planner with passive house experience11
12.01.2021Bathroom ceiling moisture + inadequate insulation44
20.01.2021Moisture seeps through the floor-to-ceiling windows in the new building34
26.02.2021(Rising?) Moisture Base / Exterior Wall11
13.03.2021Moisture in the property30
11.09.2021Which Cat cables should be installed on the facade? Problems with moisture?29
25.11.2021Getting rid of moisture from the shell construction - how to ventilate and other topics18
25.02.2022Too much moisture in the single-family house after screed installation? Risk of mold?49
19.12.2022TGA planner difficulties, underfloor heating supply temperature + wastewater ventilation124
12.09.2023Tile installation with additional costs for large format11

Oben