Hello, we have received an initial response from an architect (preliminary planning).
Basis:
120 m2 (bungalow, without basement, roof not developed with hipped roof)
double garage (solid construction, approx. 6x8m, unfortunately also with hipped roof)
Architect’s statement
Costs around €250,000 (equipment not considered, he adds)
This amount does not include the costs for outdoor facilities, furnishings, or incidental costs for planning, structural engineering, construction management, etc.
For incidental costs, you can expect about 15 to 20% of the construction costs.
So we had calculated about €200,000 but that the base or simple equipment should already cost so much really blows us away.
That makes a price per square meter of 250,000/120 m2 = €2083.33
Is all this correct!?
Basis:
120 m2 (bungalow, without basement, roof not developed with hipped roof)
double garage (solid construction, approx. 6x8m, unfortunately also with hipped roof)
Architect’s statement
Costs around €250,000 (equipment not considered, he adds)
This amount does not include the costs for outdoor facilities, furnishings, or incidental costs for planning, structural engineering, construction management, etc.
For incidental costs, you can expect about 15 to 20% of the construction costs.
So we had calculated about €200,000 but that the base or simple equipment should already cost so much really blows us away.
That makes a price per square meter of 250,000/120 m2 = €2083.33
Is all this correct!?