Exemption §67 Building Code NW rejected

  • Erstellt am 2016-01-20 08:56:49

sirhc

2016-01-20 08:56:49
  • #1
Hello everyone,

shortly before the turn of the year, we submitted our documents and applied for the exemption according to §67 Bauordnung NW. Unfortunately, this was rejected and is now being processed as a building application according to §68 Bauordnung NW.

We had attached a copy of the development plan we have and marked the parcel on it. It was pointed out that the development plan valid since 1974 (last change until then) has not been valid since July 2015 (it was incorporated into another development plan), that the floor area ratio does not correspond to BauNVO §19, and the plot ratio is missing.

What happens now if our documents are processed further as a building application (as we requested)? The result of the examination should be the same, just with a fee notice, right? There is no explicit request to improve the floor area ratio and to submit the plot ratio.

The floor area ratio is missing the secondary areas such as house access, driveway, and terrace, which are counted at 50%. A plot ratio was not mentioned in the replaced development plan but perhaps in the current development plan.

The permitted floor area ratio is 0.4 - according to our calculation, it was 0.32 without secondary areas, with secondary areas I come to 0.37. The plot ratio is at about exactly 0.25 - I do not yet know the permitted maximum value here.

I will of course get in touch with the office; I just wanted to ask in advance what I should now pay attention to on my part.

Thanks and regards
 

Bauexperte

2016-01-20 11:09:39
  • #2
Hello,


Your application contradicts the stipulations of the development plan.


That depends on how much your application deviates from the applicable development plan and cannot be answered from here. The authority initially responded within one month; the deadline was met. Now all offices involved will participate in the decision; this can take up to 3 months, depending on the difficulty of the site to be developed. The authority will inform you in writing if it needs anything further to make the decision, which documents you have to submit.

A major difference can be found in the fee notice. For the simplified approval procedure, about €50.00 is charged (in this case the authority does not review, and your architect is liable for compliance with the development plan). In the regular building application procedure, costs can rise up to approximately €1,000.00.


You should especially do that to avoid your building application being rejected without cost because papers are missing. Unfortunately, you did not mention if your planner has ticked the boxes in the designated places.

Rhenish regards
 

sirhc

2016-01-20 12:16:14
  • #3
Hello construction expert,

thank you for your feedback.

I understand the letter rather as saying that the floor area ratio was not calculated correctly and the plot ratio not calculated at all, so our documents are incomplete, but not that it contradicts the determinations of the development plan. Or where do you see that?

50 EUR only if you request a decision before the 4 weeks expire, otherwise it would have been free of charge. We are aware that now fees of 1000 EUR or more are at stake. But at least December 2015 still counts as the submission date and thus the old Energy Saving Ordinance.

Which checkbox are you referring to in the last paragraph? That is not quite clear to me.

Thanks again and best regards
 

Bauexperte

2016-01-20 12:55:59
  • #4
Hello,


Because the buildings must not contradict the provisions of the development plan, and you wrote about a change of the development plan or a transition to another one.


There is a field on the form, which is checked to serve the purpose, in case of doubt, not to reject the submitted building application with a fee, but to consult with the planner.

Rhenish regards
 

Similar topics
10.12.2012Terrain elevations in the development plan are incorrect.12
17.12.2014Building application "deferred". What does that mean?19
27.01.2016What does it mean: plot ratio 0.4, floor area ratio 1.2, floors II - II12
16.02.2016Regulations regarding development plans, any experiences?22
01.02.2017Building application is becoming increasingly complicated!20
07.06.2017Permeable traffic areas in the building application17
28.02.2018Deviation from the development plan in the new construction area is possible118
11.05.2018Construction application costs only 40 euros due to exemption application?27
09.07.2018Demolition of existing house - new construction: what does the development plan allow?11
08.08.2018Neighbor objects after approved building application69
15.08.2018Basic floor area ratio / floor area ratio for plots without a development plan: How to calculate? Experiences?18
30.12.2018Floor area number of multiple parcels22
31.07.2019Site coverage ratio, permeable paving for outdoor facilities11
19.02.2020Planning terrace and roofing50
30.11.2019Neighborhood concerns regarding exemption from the floor area ratio31
03.02.2020Floor area ratio / plot ratio in the development plan of 196811
20.10.2020NRW: Exemption procedure with minor deviation from the development plan18
30.05.2021Buy a house when the floor area ratio is exceeded?22
27.01.2025Interpretation of the 1957 development plan <-> possibilities for new construction36
30.11.2021Fee notice for building application57

Oben