Easily switch temporary power provider?

  • Erstellt am 2019-09-23 07:05:39

goalkeeper

2019-09-23 07:05:39
  • #1
Hello everyone,

next week we will have the construction power connected by NetzeBW at the construction site.

Do I then necessarily have to get their electricity or would a switch also be possible? Our current provider has very low usage prices. That would not be bad for building over the winter.
 

guckuck2

2019-09-23 07:06:27
  • #2
No, that's not possible with construction power.
 

goalkeeper

2019-09-23 07:10:11
  • #3
I have now found something from Verivox here that says it would be possible.
 

HilfeHilfe

2019-09-23 07:15:18
  • #4


just ask netze bw
 

guckuck2

2019-09-23 08:24:47
  • #5


Well, then let’s get started. Good luck.

Make sure no one runs a fan heater on it. A bit of crane, saw, and rotary hammer won’t make the bill fat.
Underfloor heating should definitely run on the proper power connection, otherwise it will get expensive.
 

Andre77

2019-09-23 13:14:17
  • #6


Funny, I have already brought up this topic here somewhere in the depths of the forum. But I am currently also in the process of initiating a change. Or rather, the order has been placed and the new provider is waiting for feedback. There are only two options, either the change is rejected due to ..... , or the change is carried out.

I'm curious.
 

Similar topics
06.12.2017Until when must construction power be taken?22
19.10.2017Temporary power supply - What costs are involved?19
05.07.2018Temporary electricity stolen - amount of compensation?17
20.07.2018Construction power or house connection? How much construction power is needed?12
19.03.2019Construction power is being connected. Does the builder have to be present?10
10.01.2022Determine construction power costs / eOn charges too much36
09.10.2024Construction electricity/construction water costs are the responsibility of the builder11

Oben