As much as the actual damage is. So at least rent and interest for the time.
Every builder has their own most pressing issue, which is why the damage scenarios differ. And as the name suggests, a penalty is supposed to hurt the contractor as well. This makes it advisable to assess it like an "increased transportation fee" significantly above the damage equivalent. By the way, a completion guarantee does not replace it. On the other hand, the contractor is already burdened by not yet receiving their next payment tranche triggered by the construction progress until acceptance / resolved complaint. Unfortunately, nowadays many builders work with general contractors who are undercapitalized repair procrastinators. : 10% of what exactly?50 EUR/working day is a decent compensation, in case of doubt you won't get more anyway. And if you don't like that, you just have to negotiate a 10% penalty... but of course before(!) signing the contract...