Construction delay without completion. The house simply is not finished

  • Erstellt am 2022-06-30 13:14:57

Danieltt

2022-06-30 13:14:57
  • #1
Hello everyone,

I would like to know if you have had similar experiences or if you possibly have a helpful tip on how to best deal with the situation.

At the beginning of 2021, we bought a terraced house through a small developer in NRW. The planned completion was 12/2021. However, 03/2022 was stipulated in the notarial contract.

Now it is already 07/2022 and currently only the shell including windows and electrical wiring is finished.

It is such that for weeks nothing happens on the construction site and then sporadically a craftsman works on it. Throughout the entire year 2022, work was done on the house maybe 20 days.

The flat roof has been in progress for 4 months and is still not finished.

We are repeatedly put off by the developer and assured that everyone is making an effort to move things forward. (Sometimes someone is sick because of Corona or the craftsmen don’t come or the windows are not delivered, etc.)

However, we do not receive any current completion date or written information about a delay or a planned completion.

Have you had similar experiences? Has this approach become normal during Corona times? Have you had similar delays in house construction?

Do we even have any way to take action against this?
 

Neubau2022

2022-06-30 14:43:37
  • #2


The first question would be, what are the penalties that were recorded in the contract if the developer did not finish by 03/2022?

We are currently building with a general contractor. The start was 11/2021. House handover was supposed to be 07/2022. But we rather expect 08 or 09/2022. He also agreed on a 10-month construction time guarantee in the contract with a €200 penalty per day for non-compliance. Even if it is then October, we will definitely not enforce that because we are satisfied with him so far.

That there can be problems due to delivery bottlenecks is normal nowadays. But that in half a year only a maximum of 20 days of work were done is rather not normal. I suspect the general contractor has a few more construction sites and that’s why the whole thing is delayed for you? Get together with the other builders and put some pressure on.
 

Danieltt

2022-06-30 15:06:33
  • #3
Yes, he is actually building all 14 terraced houses in parallel. He may have somewhat overestimated himself.

We have now agreed that all incurred costs will be invoiced. (double rent / availability interest, etc.). We will send a list monthly. A fixed contractual penalty was not agreed upon.

But we probably won't see the money until the end, offset.

However, we are running out of ideas on how else we could build pressure.
 

WilderSueden

2022-06-30 15:18:09
  • #4
Communication in the construction industry seems to be somewhat tedious in general, and almost everyone is likely to experience delays. For example, work on my roof has been going on forever, seemingly only when the carpenters have a day off (no pressure since the roof tiles are not yet available...).

However, there could also be another problem. I don’t want to scare you, but some companies have clearly miscalculated the price increases. If there are 14 row houses where nothing is progressing, I would also consider the possibility of an impending insolvency. One indication of this seems to be endless delays and hardly any work being done anymore. In this case, it would primarily be about securing your claims. But it’s difficult to say from a remote diagnosis.
 

SoL

2022-06-30 15:21:36
  • #5
No agreement = bad luck He’s already accommodating you with the cost coverage. You’re lucky there.
 

Danieltt

2022-06-30 15:35:19
  • #6


We have already thought that the money might simply be running short there. But we just have to wait, right?
 

Similar topics
06.02.2013Developer says: No more insulation!12
23.03.2011Developer or architect?15
15.03.2016Developer changes plot size25
25.08.2019Solid prefab house or developer - experiences?33
04.03.2019Client-side while building with a property developer16
06.08.2019First conversation with the developer - first numbers...64
10.09.2019Trouble with the property developer, don't know what to do anymore13
15.09.2019Developer refuses to hand over documents32
23.12.2019Plot of land - Can you still build today without a developer?64
09.06.2020False statement by sales partner at developer12
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
13.09.2020BAFA funding for heat pump (air-to-water heat pump) when building with a developer25
06.01.2021Purchase from the developer at the end of the year - Financial assessment12
06.05.2022Looking for developers in SH - experiences28
06.02.2021The developer requires a down payment to start drawing42
16.05.2021Approach for Initial Contact with Property Developers & Prefabricated Building Suppliers24
09.09.2021KfW 261 if the developer has already applied for funding11
08.12.2021Would you build yourself again or use a developer?31
25.12.2023Behavior in case of imminent delay by the property developer48

Oben