Hello everyone,

we are about to agree on a construction contract in addition to the construction and performance description. Do you have any tips on what should definitely be included? What was missing for you and unexpectedly caused additional costs afterwards? What experiences do you have with negotiating additional services? Where did it work for you and with which arguments?
Thank you very much for your tips
 

Gerddieter

2023-04-17 20:34:42
  • #2
1. Write down everything, really everything that is important to you and also price it!!! In our example, the wood-aluminum option was important and we were convinced to only write plastic into the contract, and the surcharge would then be calculated during the sampling... for us now clearly the worse position. 2. Make everything really everything optionally removable where you have doubts that the general contractor can implement it according to your wishes...

GD
 

allstar83

2023-04-17 23:41:38
  • #3
I would include everything that the contractor doesn't find difficult to do. For example, any foundations or a slab for a shed, gravel for the yard, etc. In the end, for example, I negotiated the concrete terrace as a discount. But to be fair, I must also say that the contract had no price increases. I think that no longer exists. However, I forgot things like green roofing, etc. Additional charges were fair for us as well. Although the prices always do shock you a bit, considering what it actually costs.
 

kati1337

2023-04-18 12:54:55
  • #4
Apart from the already mentioned things, it should always include when the construction starts, how long until completion, whether it is a fixed price, and how long the price is binding.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18
06.09.2024Contractual penalty in the Building Code contract - new construction20