Silke._.
2023-10-01 10:58:27
- #1
Hello everyone,
I have a question about our construction project (new single-family house in NRW) and would appreciate your opinions, as I haven’t really made any progress with my own research. Unfortunately, our architect and construction company have different opinions about what is necessary and what is not.
About the problem:
According to the planning documents for the building permit, our exterior walls have a thickness of 36.5 cm. After the building permit was issued, a verification was created regarding energy savings and the use of renewable energies for heating and cooling generation in buildings. According to this verification, the exterior walls must have a thickness of 40 cm.
Our architect thinks that we can simply adjust the exterior dimensions of the house (previously: 8.49 m x 8.99 m, adjusted: 8.56 m x 9.06 m) accordingly and only need to shift the house by 4 cm on one side of the plot, since a boundary distance of 3 m was previously planned here. The boundary distances to all other sides would also be maintained with the changed exterior dimensions. No further measures except for adjustment by a surveyor would be necessary.
Our construction company says that we cannot simply deviate from the building permit to this extent. They propose an amendment of the plans, keeping the exterior dimensions of the house and changing the interior dimensions accordingly. But regardless of whether the exterior dimensions are adjusted or not, the construction company wants new plans from our architect. Otherwise, additional costs will arise due to the changed exterior dimensions, and they want to make an additional contractual agreement in this regard.
My question is, is the adjustment of the exterior dimensions and the corresponding shift still within any tolerance limits or do we need a supplementary approval / alteration to the building application? What other measures are necessary when adjusting the exterior walls either while maintaining the exterior dimensions or adjusting them? Does a new static calculation have to be done?
Unfortunately, our architect is on vacation for an extended period now and the construction company wants to begin with the foundation slab the week after next.
Personally, I would like to keep the exterior dimensions and ask our architect to adjust the plans accordingly. In my opinion, that would be the most practical solution. Since there is already a building permit in place, our floor plan would allow a corresponding reduction, no additional costs would arise with the construction company, and I hope that only plan changes from our architect are sufficient and that we do not need a new static calculation.
Thank you very much and best regards from Rhein-Sieg-Kreis!
I have a question about our construction project (new single-family house in NRW) and would appreciate your opinions, as I haven’t really made any progress with my own research. Unfortunately, our architect and construction company have different opinions about what is necessary and what is not.
About the problem:
According to the planning documents for the building permit, our exterior walls have a thickness of 36.5 cm. After the building permit was issued, a verification was created regarding energy savings and the use of renewable energies for heating and cooling generation in buildings. According to this verification, the exterior walls must have a thickness of 40 cm.
Our architect thinks that we can simply adjust the exterior dimensions of the house (previously: 8.49 m x 8.99 m, adjusted: 8.56 m x 9.06 m) accordingly and only need to shift the house by 4 cm on one side of the plot, since a boundary distance of 3 m was previously planned here. The boundary distances to all other sides would also be maintained with the changed exterior dimensions. No further measures except for adjustment by a surveyor would be necessary.
Our construction company says that we cannot simply deviate from the building permit to this extent. They propose an amendment of the plans, keeping the exterior dimensions of the house and changing the interior dimensions accordingly. But regardless of whether the exterior dimensions are adjusted or not, the construction company wants new plans from our architect. Otherwise, additional costs will arise due to the changed exterior dimensions, and they want to make an additional contractual agreement in this regard.
My question is, is the adjustment of the exterior dimensions and the corresponding shift still within any tolerance limits or do we need a supplementary approval / alteration to the building application? What other measures are necessary when adjusting the exterior walls either while maintaining the exterior dimensions or adjusting them? Does a new static calculation have to be done?
Unfortunately, our architect is on vacation for an extended period now and the construction company wants to begin with the foundation slab the week after next.
Personally, I would like to keep the exterior dimensions and ask our architect to adjust the plans accordingly. In my opinion, that would be the most practical solution. Since there is already a building permit in place, our floor plan would allow a corresponding reduction, no additional costs would arise with the construction company, and I hope that only plan changes from our architect are sufficient and that we do not need a new static calculation.
Thank you very much and best regards from Rhein-Sieg-Kreis!