Thomas911
2021-07-25 10:02:16
- #1
Hello everyone,
unfortunately, I have to ask for your expert opinion again, as I currently only have friction and an uneasy feeling with our construction company.
We have already had so many points of contention without the construction even starting.
Now the good gentleman, the owner of the construction company, informed us that he would like to have an assignment declaration from us. This clearly creates a disadvantage/high risk for us.
It is now the case that the construction company is contractually entitled to demand this service from us.
The contract includes the following clause – see the attachment. Unfortunately, it was indeed the case that we were late with the first installment. This was due to the fact that the registration in the land register had not yet taken place at that time, and the bank refused to pay out to the construction company until the registration was completed. We had agreed on this with the construction financing, which is why the payment delay occurred. However, this clause regarding the assignment declaration slipped past us.
Is there now a possibility for us not to comply with the construction company's demand? What happens in the case that we refuse such an obligation? Once again our own mistake, I know, but can it be that such a situation is legally legitimate when it causes a significant disadvantage for the builder?
Thanks in advance.

unfortunately, I have to ask for your expert opinion again, as I currently only have friction and an uneasy feeling with our construction company.
We have already had so many points of contention without the construction even starting.
Now the good gentleman, the owner of the construction company, informed us that he would like to have an assignment declaration from us. This clearly creates a disadvantage/high risk for us.
It is now the case that the construction company is contractually entitled to demand this service from us.
The contract includes the following clause – see the attachment. Unfortunately, it was indeed the case that we were late with the first installment. This was due to the fact that the registration in the land register had not yet taken place at that time, and the bank refused to pay out to the construction company until the registration was completed. We had agreed on this with the construction financing, which is why the payment delay occurred. However, this clause regarding the assignment declaration slipped past us.
Is there now a possibility for us not to comply with the construction company's demand? What happens in the case that we refuse such an obligation? Once again our own mistake, I know, but can it be that such a situation is legally legitimate when it causes a significant disadvantage for the builder?
Thanks in advance.