stefanc84
2017-12-11 13:37:40
- #1
Hello,
our construction company wants to install the screed (cement, not flowing screed) shortly before Christmas. The heating will then be put into operation only 3 weeks later due to the holiday period.
=> It is recommended to dry for 14 days, then use a heating program. Do you see a problem with the 3 weeks without heating?
Shortly before the heating is put into operation, the technical room is to be tiled. This would be done by a tiler separately commissioned by us, and he is supposed to use PCI adhesive because the screed is not yet dry.
=> Elsewhere I have read that PCI adhesive should only be used within the first 5 days, that is only on very fresh screed. Ours will then be almost 3 weeks old. How do you assess this? Will that be botched?
The construction company makes it easy with their demand; they do not have to assume any warranty for the tiles, as it is our tiler.
Finally, a question about the reason why it should be tiled beforehand.
The multi-utility introduction will be completed/sealed shortly afterward. And it is supposed to sit ON the tiles (on the floor).
=> Why? Why can’t you just wait until everything is dry and then tile around the floor introduction on the outside?
I find all this somewhat strange and have the feeling that it is only being done this way because it fits well into the construction company’s schedule...
our construction company wants to install the screed (cement, not flowing screed) shortly before Christmas. The heating will then be put into operation only 3 weeks later due to the holiday period.
=> It is recommended to dry for 14 days, then use a heating program. Do you see a problem with the 3 weeks without heating?
Shortly before the heating is put into operation, the technical room is to be tiled. This would be done by a tiler separately commissioned by us, and he is supposed to use PCI adhesive because the screed is not yet dry.
=> Elsewhere I have read that PCI adhesive should only be used within the first 5 days, that is only on very fresh screed. Ours will then be almost 3 weeks old. How do you assess this? Will that be botched?
The construction company makes it easy with their demand; they do not have to assume any warranty for the tiles, as it is our tiler.
Finally, a question about the reason why it should be tiled beforehand.
The multi-utility introduction will be completed/sealed shortly afterward. And it is supposed to sit ON the tiles (on the floor).
=> Why? Why can’t you just wait until everything is dry and then tile around the floor introduction on the outside?
I find all this somewhat strange and have the feeling that it is only being done this way because it fits well into the construction company’s schedule...