Berlin front structure for securing the excavation pit

  • Erstellt am 2023-09-21 10:54:42

Bayernbors

2023-09-21 10:54:42
  • #1
Hello everyone,

There are several problems with the excavation pit in our construction project. The general contractor says that the planned house is large (2 semi-detached houses, each 11*7) and the plot is small (~450 m2), which brings some technical difficulties.

The work on the excavation pit began with the demolition of the old house, since it already had a basement.

The bad part is that we are only discovering all these problems gradually and not as expected in the original planning:

1) Initially, it turned out that the edges of the excavation pit are weak and we need a support for the crane, which is why a crane foundation was built.
2) Secondly, it was found that the plot is still too small for the crane, and a permit was required to set up the crane (partially) on the sidewalk.

The first two steps were completed at the end of June, and then the work was completely stopped (except for the erection of the crane).

At the end of August, my new neighbors contacted me and were concerned because they see that the sides of the pit are slipping more and more, causing the pit to incline toward their property and the slope stability is no longer guaranteed.

At this point, the general contractor says they have already discussed this problem with the various authorities. They suggested increasing the slope of the pit, but this proposal was rejected because it would affect the sidewalk.

The only remaining solution was then to provide a bond to maintain the durability of the sidewalk.

After an additional geotechnical investigation, it was determined that the sheet piling is required on all sides and not just on the sidewalk.

My questions are:
Does all this make sense?
Does it make sense to find out these problems so late? Does it really take about 3 months to come to this result? Should I hold the general contractor accountable for these delays?
Note: At the end of June, I agreed with the general contractor that the house should be finished by the end of February 2024, as our contract states: "The contractor undertakes to complete the contract object ready for occupancy within 8 months from the excavation, provided weather conditions permit."

Finally, how much time should I expect to complete this Berliner retaining wall and finally start construction?
I have read online that the costs could amount to several tens of thousands; is that realistic?

Thank you very much
Best regards
 

Cronos86

2023-09-21 11:35:04
  • #2
Hi,

in general, the soil conditions should already have been described in the original soil survey report (which of course was done before the work started)! Here we have a clay soil (loess? perhaps with a higher sand content? I unfortunately can’t tell from the pictures). With firm consistency, it should be sloped at a maximum of 60°. If there is more sand, only at 45° (but in the pictures it looks more like 60°). The planner should of course immediately have all alarm bells ringing when planning the excavation (footprint + working space + slope). If it then cuts into the sidewalk, it is obvious that shoring must be used. I would also prefer a Berlin strut here. I do not see a necessity to make the shoring continuous based on the pictures (just upload a site plan with basement or excavation). A layer profile from the soil report wouldn't hurt either. Then such soils must be immediately sloped after exposure to prevent water ingress and to avoid slope failure.

The distances to the neighbors actually still look quite good.
For neighboring buildings, the following always applies:
-never fully expose the foundations!
-the load distribution of the neighbor’s foundations must not cut into your slope (bottom edge of foundation with a load distribution of 45°). Unless you have shoring!

Best regards
 

hanghaus2023

2023-09-21 13:19:00
  • #3
Image 1 Changing the slope at the bottom to 90 degrees is fatal.

Image 2 already looks quite borderline. The slope goes up to the neighbor's house. Leaving the excavation pit like this permanently is grossly negligent.

Image 3 doesn't say anything.

Meaningful images and plans are quite helpful.
 

11ant

2023-09-21 19:07:08
  • #4

At least a site plan excerpt can be seen here: , and there are more surrounding pictures here:

It's a pity that some original posters with the necessary consultative insights are stingy and only come back when the pedal boat is already in distress. There is certainly enough expertise gathered here to help people who speak early enough.
 

hanghaus2023

2023-09-21 19:41:48
  • #5
I will reply directly in your text.


Hopefully things will be planned better going forward here.
 

Bayernbors

2023-09-26 16:32:41
  • #6
Thank you very much for the feedback. I was on a trip abroad. The photos I sent were a bit old, so I have now taken new ones. The general contractor has so far covered one side of the excavation pit; I am not sure if that is really useful.

I am attaching the new photos and parts of the report here, since I cannot attach a PDF file here.


Does that also apply to the 2 neighbors? When I look again, it seems the excavation pit has exposed the foundation of the neighbor to the east (seems to have no basement).
The northern neighbor was the concerned one, and I think that is because he has a garage on the border.


They only say that the property is very difficult and something like: "Who could have known all these problems from the start!"


Yes, only when they tried to set up the crane.


That is not entirely clear. From your point of view, what should have been done in this case?
The municipality also closed the streets (completely or partially) because the stability of the street is no longer guaranteed (at least that is their point of view).















 

Similar topics
31.12.2014Get training equipment in the basement (new building)?14
04.03.2015Budget plot and building with basement21
30.09.2019200m2 single-family house for 4-5 people without a basement on a narrow plot67
22.12.2019Crane from the neighbor on my property67
19.11.2019Preliminary contract for land due to soil survey17
27.06.2020Level the basement or the plot?43
28.07.2020Single-family house 160m2 with basement, 500m2 plot108
09.07.2020Soil replacement up to 1.20m depth - fill or basement?11
09.10.2020Single-family house 220 sqm with basement on 700 sqm plot41
15.07.2020Soil survey even if I don't build a basement?13
19.10.2020Street about 50cm above the property - backfill or basement24
22.01.2024Construction progress: Duplex with WU basement and developed attic813
12.07.2021Hang property, catch carport22
11.01.2022House floor plan (access via slope)21
04.03.2022Property development - basement yes or no?75
20.12.2022Lowering of groundwater according to soil report - Your experiences?57
04.05.2022Load-bearing capacity of L-stone and water drainage at 45° slope54
24.09.2022Neighbor grounding and drainage on our property41
20.03.2023What is the space requirement for earthworks in construction with a basement?10
31.07.2023Is a soil survey necessary when a geotechnical report is available?17

Oben