Bayernbors
2023-09-21 10:54:42
- #1
Hello everyone,
There are several problems with the excavation pit in our construction project. The general contractor says that the planned house is large (2 semi-detached houses, each 11*7) and the plot is small (~450 m2), which brings some technical difficulties.
The work on the excavation pit began with the demolition of the old house, since it already had a basement.
The bad part is that we are only discovering all these problems gradually and not as expected in the original planning:
1) Initially, it turned out that the edges of the excavation pit are weak and we need a support for the crane, which is why a crane foundation was built.
2) Secondly, it was found that the plot is still too small for the crane, and a permit was required to set up the crane (partially) on the sidewalk.
The first two steps were completed at the end of June, and then the work was completely stopped (except for the erection of the crane).
At the end of August, my new neighbors contacted me and were concerned because they see that the sides of the pit are slipping more and more, causing the pit to incline toward their property and the slope stability is no longer guaranteed.
At this point, the general contractor says they have already discussed this problem with the various authorities. They suggested increasing the slope of the pit, but this proposal was rejected because it would affect the sidewalk.
The only remaining solution was then to provide a bond to maintain the durability of the sidewalk.
After an additional geotechnical investigation, it was determined that the sheet piling is required on all sides and not just on the sidewalk.
My questions are:
Does all this make sense?
Does it make sense to find out these problems so late? Does it really take about 3 months to come to this result? Should I hold the general contractor accountable for these delays?
Note: At the end of June, I agreed with the general contractor that the house should be finished by the end of February 2024, as our contract states: "The contractor undertakes to complete the contract object ready for occupancy within 8 months from the excavation, provided weather conditions permit."
Finally, how much time should I expect to complete this Berliner retaining wall and finally start construction?
I have read online that the costs could amount to several tens of thousands; is that realistic?
Thank you very much
Best regards
There are several problems with the excavation pit in our construction project. The general contractor says that the planned house is large (2 semi-detached houses, each 11*7) and the plot is small (~450 m2), which brings some technical difficulties.
The work on the excavation pit began with the demolition of the old house, since it already had a basement.
The bad part is that we are only discovering all these problems gradually and not as expected in the original planning:
1) Initially, it turned out that the edges of the excavation pit are weak and we need a support for the crane, which is why a crane foundation was built.
2) Secondly, it was found that the plot is still too small for the crane, and a permit was required to set up the crane (partially) on the sidewalk.
The first two steps were completed at the end of June, and then the work was completely stopped (except for the erection of the crane).
At the end of August, my new neighbors contacted me and were concerned because they see that the sides of the pit are slipping more and more, causing the pit to incline toward their property and the slope stability is no longer guaranteed.
At this point, the general contractor says they have already discussed this problem with the various authorities. They suggested increasing the slope of the pit, but this proposal was rejected because it would affect the sidewalk.
The only remaining solution was then to provide a bond to maintain the durability of the sidewalk.
After an additional geotechnical investigation, it was determined that the sheet piling is required on all sides and not just on the sidewalk.
My questions are:
Does all this make sense?
Does it make sense to find out these problems so late? Does it really take about 3 months to come to this result? Should I hold the general contractor accountable for these delays?
Note: At the end of June, I agreed with the general contractor that the house should be finished by the end of February 2024, as our contract states: "The contractor undertakes to complete the contract object ready for occupancy within 8 months from the excavation, provided weather conditions permit."
Finally, how much time should I expect to complete this Berliner retaining wall and finally start construction?
I have read online that the costs could amount to several tens of thousands; is that realistic?
Thank you very much
Best regards