Hello,
we had a house built under a VOB contract and the handover/acceptance is scheduled soon. On this key date, we are to transfer the final installment. Basically, this is also possible from my point of view, but I am annoyed by a deviation from the drawing. I would prefer a discount because it was not done as shown in the drawing.
The site management denies everything, everything is present, but one detail was simply not built according to the drawing.
Now the question is: according to my understanding, the deal is done as soon as I have paid in full, meaning there is no prospect of claiming anything further or insisting on construction according to the drawing. The final installment is basically intended to serve as a means of leverage. On the other hand, the move-in date is approaching, and we want to avoid further double burdens.
What course of action would be advisable here?
Thanks in advance for any useful advice...
we had a house built under a VOB contract and the handover/acceptance is scheduled soon. On this key date, we are to transfer the final installment. Basically, this is also possible from my point of view, but I am annoyed by a deviation from the drawing. I would prefer a discount because it was not done as shown in the drawing.
The site management denies everything, everything is present, but one detail was simply not built according to the drawing.
Now the question is: according to my understanding, the deal is done as soon as I have paid in full, meaning there is no prospect of claiming anything further or insisting on construction according to the drawing. The final installment is basically intended to serve as a means of leverage. On the other hand, the move-in date is approaching, and we want to avoid further double burdens.
What course of action would be advisable here?
Thanks in advance for any useful advice...