KlaRa
2022-09-16 11:03:33
- #1
A decoupling mat cannot conceal the permissible unevenness of a floor slab according to DIN 18202 Table 3 Row 2, nor the "usual roughness" after its production. Therefore, the flatness and the post-treatment measure (e.g. mechanical grinding) must already be specified in the tender of the floor slab. If this was not or is not the case, the concrete surface must be assessed in detail. However, this is only possible if a mechanical surface treatment (shot blasting for large areas, brushing or grinding for smaller areas) was carried out beforehand. In principle, tiles or natural stones can be laid in a medium bed process on a correspondingly load-bearing and sufficiently even concrete surface. But even then there are some things to consider, which is why a layperson should not undertake these tasks without professional assistance (adequate pre-wetting, for example). Regards: KlaRa