Base plate - Reinforcement / Sink & Quality

  • Erstellt am 2018-12-16 12:31:11

HausbauTiNa

2018-12-16 12:31:11
  • #1
Hello everyone,

our house construction has started and the first steps such as earthworks and strip foundations have already been completed. The base slab has been prepared for concreting.

I have the following questions:

Earthworks:
For the earthworks, according to the soil investigation, 60 cm of topsoil was removed and replaced and compacted with fill sand accordingly. However, it has been shown that on one side of the house in the area of the strip foundation, about 10 cm were removed too little (see photo in the attachment). How critical do you see something like this?

Strip foundations:
The strip foundations (80 cm deep with round cages) were not shuttered. How can the L-barrier be properly applied later here without a clean edge? What do you think about the inserted irons currently used as holders for the formwork?

Base slab:
Hauff sleeves for wastewater penetrations were installed in the base slab, which I see as positive. However, it is also visually apparent that the sand bed in the middle of the slab has a strong depression. Upon closer inspection, extra thick reinforcement can also be seen there. Could this possibly be due to load-bearing walls?

I look forward to your answers, as the slab is supposed to be concreted on 17.12.2018.

What is your overall visual impression?

Thank you very much






 

Bookstar

2018-12-16 13:12:31
  • #2
My opinion: this is not how you will get through building the house and it will be extremely exhausting. Don't you have anyone who knows about this and can supervise it?
 

HausbauTiNa

2018-12-16 13:47:11
  • #3


This response does not help me without fundamental reasons.
I do believe that we are quite capable of getting through the house construction. However, that it will be exhausting is another matter.

What matters to me here is the assessment of the aforementioned topics by third parties.
We know each other, partly due to our professions, but there are areas of expertise, as mentioned above, where I would like to hear another opinion.

When the topic of experts comes up:
We had discussions, but they were anything but convincing. One even went so far as to say that I have to work much more responsibly in my job than he does. Also, those visited (by the way from the Bauherren-Schutzbund, which we are now leaving again) were not able to explain a meaningful staging of the payment plan, nor to address further construction priorities.
 

Tom1607

2018-12-16 16:25:57
  • #4
Hi,

giving a diagnosis from a distance is always difficult. To me, everything looks normal so far. Since your floor slab is a ground-contacting component, a vapor barrier will be installed inside anyway. The connection to the foundation should not be a problem and the few rebars should also not cause a big issue. The fact that less topsoil was removed than agreed upon should be a matter for the invoice. Topsoil settles significantly less than fill material, even if compacted. The depression is not a big deal; more concrete will just be poured in, at the expense of the contractor. Also interesting is that there apparently is no insulation under the floor slab. This is hardly ever seen nowadays anyway.

As an electrician, I find the topic of grounding/potential equalization more interesting. Normally, the reinforcing steel mats have to be included in the grounding. For this purpose, usually a steel strip is laid all around once and connected to the reinforcing steel mats every 2 meters. This is regulated in DIN18015-1. You should take a look at it before they pour the slab tomorrow.

And installing and documenting this must be done by an electrician, not like before by the bricklayer.

Otherwise, I wish you lots of fun with the house building project!!
 

HausbauTiNa

2018-12-16 16:52:03
  • #5


Hello Tom,

thank you very much for the reply and the wishes.

We decided against the insulation.
The strip steel is installed all around in the strip foundation and is also connected.
 

paul1287

2019-04-10 18:54:11
  • #6
Hi, our house was also built on strip foundations and there is nothing negative to say about the fastening with iron. Our construction manager from Prime Massivhaus told us that it is important that the iron is completely encased by the concrete so that it cannot rust. So I wouldn't worry about this issue.
 

Similar topics
05.06.2010Basement made of high perforated bricks or concrete?11
31.05.2015Wastewater pipe concreted in the floor slab at the wrong location29
26.10.2012External perimeter insulation floor slab, basement mold risk11
15.06.2015Base slab or strip foundations for garage12
11.09.2016Base plate - construction/insulation etc. - experiences please!10
11.10.2017Sealing on Styrodur insulation?14
13.09.2016Insulation under the floor slab EPS or XPS?12
06.10.2016Base plate with defects?22
27.11.2016Double insulation below and above the floor slab?10
26.02.2018Insulation under reinforced concrete floor slab KFW5520
29.10.2018Earthworks in the construction performance description17
09.02.2019Ground slab with strip foundation and frost skirt23
29.12.2020Y-Tong vs Concrete without extra insulation in practice (heating costs)38
01.07.2019KFW 55 - Insulation under the floor slab37
02.02.2020Insulation under the floor slab - Is it sensible? Experiences39
27.05.2020Set formwork blocks on the foundation or in concrete21
30.06.2020Base plate, too little cement in the concrete19
15.03.2022Cost planning for earthworks33
29.04.2025Insulation of the ground slab in the basement with thermal stone12

Oben