HausbauTiNa
2018-12-16 12:31:11
- #1
Hello everyone,
our house construction has started and the first steps such as earthworks and strip foundations have already been completed. The base slab has been prepared for concreting.
I have the following questions:
Earthworks:
For the earthworks, according to the soil investigation, 60 cm of topsoil was removed and replaced and compacted with fill sand accordingly. However, it has been shown that on one side of the house in the area of the strip foundation, about 10 cm were removed too little (see photo in the attachment). How critical do you see something like this?
Strip foundations:
The strip foundations (80 cm deep with round cages) were not shuttered. How can the L-barrier be properly applied later here without a clean edge? What do you think about the inserted irons currently used as holders for the formwork?
Base slab:
Hauff sleeves for wastewater penetrations were installed in the base slab, which I see as positive. However, it is also visually apparent that the sand bed in the middle of the slab has a strong depression. Upon closer inspection, extra thick reinforcement can also be seen there. Could this possibly be due to load-bearing walls?
I look forward to your answers, as the slab is supposed to be concreted on 17.12.2018.
What is your overall visual impression?
Thank you very much

our house construction has started and the first steps such as earthworks and strip foundations have already been completed. The base slab has been prepared for concreting.
I have the following questions:
Earthworks:
For the earthworks, according to the soil investigation, 60 cm of topsoil was removed and replaced and compacted with fill sand accordingly. However, it has been shown that on one side of the house in the area of the strip foundation, about 10 cm were removed too little (see photo in the attachment). How critical do you see something like this?
Strip foundations:
The strip foundations (80 cm deep with round cages) were not shuttered. How can the L-barrier be properly applied later here without a clean edge? What do you think about the inserted irons currently used as holders for the formwork?
Base slab:
Hauff sleeves for wastewater penetrations were installed in the base slab, which I see as positive. However, it is also visually apparent that the sand bed in the middle of the slab has a strong depression. Upon closer inspection, extra thick reinforcement can also be seen there. Could this possibly be due to load-bearing walls?
I look forward to your answers, as the slab is supposed to be concreted on 17.12.2018.
What is your overall visual impression?
Thank you very much