Base plate on special property, please note

  • Erstellt am 2014-11-03 05:42:51

Xinette

2014-11-03 05:42:51
  • #1
Hello everyone,

We are planning to buy a plot of land in a new development area. Nothing has been built there yet. Construction start 2015.
The soil was replaced up to 4 m high due to contamination. Then sand was added again and each layer was compacted with heavy machinery. Residents could confirm this to us. Finally, topsoil was applied and compacted again. You can actually walk on it without sinking.
What do you think, does it make sense to build on it, or will the ground still settle so much that settlement cracks are likely? Should we expect additional costs for the foundation slab?
Best regards, Xinette
 

Musketier

2014-11-03 07:26:22
  • #2
At our place, the building plot was prepared similarly. Former factory, up to 6m soil replacement (less in our case) and layered filling including compaction with heavy machinery.

The soil survey then provides the certainty of what additional measures need to be taken. If I remember correctly, the foundation slab then had to be reinforced with additional steel mesh and an extra layer of gravel had to be added. If everything had been calculated for us, it would have cost us all inclusive around 4,000€. However, I have also heard from builders in the construction area that they had to pay more because more soil had to be replaced.
 

Bauherren2014

2014-11-03 11:20:38
  • #3
You can actually only be advised to have a soil survey carried out (preferably before purchase). Only then will you know whether and to what extent additional costs for earthworks (e.g. soil replacement) or the foundation slab are to be expected. Of course, this also always depends on whether you want to build with or without a basement. Perhaps it would also be sensible to carry out a contaminated site investigation.
 

Musketier

2014-11-03 11:30:22
  • #4
With us, the developer had to provide the responsible authority with proof/report that the contaminated sites have been cleared. Only then were the building applications processed.
 

Xinette

2014-11-03 14:06:47
  • #5
At least the old contaminants are gone. Soil samples were taken constantly. We will see if there might be other samples as well. But I also think that despite solidification, there is a possibility of further settlement. Best regards Xinette
 

Musketier

2014-11-03 14:25:04
  • #6
You need the soil report anyway, it's no big deal. Unfortunately, we couldn't have a soil report made before purchasing the plot and before signing the loan agreement. That was one of the big unknowns in our calculation.
 

Similar topics
18.09.2012Construction of a base slab with frost skirt but without foundation10
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
24.07.2014Soil assessment report, filling - additional costs?11
23.11.2014Soil report shocked us!!34
10.08.2016Soil report - silty and artificial fill11
20.08.2016Base slab vs strip foundation15
29.07.2018Perimeter insulation under the floor slab and still XPS under the screed?28
27.11.2016Double insulation below and above the floor slab?10
27.03.2017Backfilling for foundation slab25
22.06.2018Unauthorized high-quality work - additional costs25
14.11.2019Construction contract additional costs foundation reinforcement?10
30.05.2020Support hanging and filling - Additional costs?31
10.07.2020Assessment of Soil Report - Experiences14
15.07.2020Soil survey even if I don't build a basement?13
09.07.2021First alleged fixed price and now additional costs - legal?79
27.11.2021Ancillary construction costs for earthworks according to soil report16
20.12.2022Lowering of groundwater according to soil report - Your experiences?57
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
31.07.2023Is a soil survey necessary when a geotechnical report is available?17
03.03.2024Basement or ground slab: which is more sensible for the property situation?55

Oben