2018-08-25 16:28:04
- #1
Hello everyone,
we have found a plot of land that will be divided and then each part will be built with a semi-detached house (on-site near Cologne). Now we have a first offer for a semi-detached house in solid construction. We would like to get a better feeling for how to assess the offer. We would be very happy about your help!
Here are the main key data:
280,000 euros are requested for this. Added is a full basement (black tank) as a utility basement for 62,000 euros. Ancillary construction costs of 35,000 euros are planned.
We estimate the equipment listed in the scope of work description as a medium standard. Therefore, some additional costs will certainly arise here.
Is it possible to make an initial estimate on this basis?
Best regards
Paul
we have found a plot of land that will be divided and then each part will be built with a semi-detached house (on-site near Cologne). Now we have a first offer for a semi-detached house in solid construction. We would like to get a better feeling for how to assess the offer. We would be very happy about your help!
Here are the main key data:
[*
- 1.5 stories (restriction according to development plan)
[*]Footprint 7 x 14 meters
[*]approx. 150 square meters area according to DIN 277 (actual living area is lower because the knee wall height in the attic is only 0.5 m)
[*]Energy-saving house according to the Energy Saving Ordinance
[*]Exterior and interior walls made of Ytong
[*]Floor slab
[*]Turnkey according to construction/performance description, that means:
[LIST]
[*]Electrical installation, materials and assembly
[*]Sanitary installation, materials and assembly
[*]Gable roof construction
[*]Windows with triple glazing and security class RC2N
[*]Belt roller shutters
[*]Plastic front door with mushroom head lock
[*]Steel stringer staircase with beech steps
[*]Interior doors made of tube core (CPL coated)
[*]Gas condensing boiler
[*]Underfloor heating on ground floor and attic
[*]Without wall and floor coverings
280,000 euros are requested for this. Added is a full basement (black tank) as a utility basement for 62,000 euros. Ancillary construction costs of 35,000 euros are planned.
We estimate the equipment listed in the scope of work description as a medium standard. Therefore, some additional costs will certainly arise here.
Is it possible to make an initial estimate on this basis?
Best regards
Paul