for our construction project, we joined BHS and now have a construction supervisor there. He has noted the following inspection appointments in his contract. Since each appearance costs money (travel, inspection, return trip, follow-up), I wanted to know if, from your point of view, all the individual inspections are really necessary? There are apparently 8 inspections, during which a total of 13 topics are reviewed.

    [*]Inspection of foundation work / base plate before concreting the slab
    [*]Inspection of basement walls after waterproofing / before backfilling the excavation -> we do not have a basement
    [*]Inspection of shell construction after erection of the roof truss
    [*]Inspection of roof after roofing and roofing sheet metal work
    [*]Inspection of windows after installation and before interior plastering
    [*]Inspection of rough installation of building services before concealing the lines
    [*]Inspection of interior plaster / drywall (*)
    [*]Inspection of screed preparation before installing screed
    [*]Inspection of tiling work after waterproofing sanitary rooms and before tiling
    [*]Inspection of facade work (*)
    [*]Inspection of interior finishing (*) / inspection of building services (*)
    [*]Pre-inspection for final acceptance (*)
    [*]Technical supervision for final acceptance

(*) in connection with other inspection appointments

Estimated costs according to the construction supervisor approx. €3000.
 

Altai

2019-11-15 08:43:33
  • #2
What would you want to cancel? I can't think of anything.
 

vaderle

2019-11-15 08:53:17
  • #3
Well, if those are the standard dates, I wouldn't deselect anything. Only if someone were to say "This checkpoint is completely unnecessary because you can't see anything there anyway." If such feedback doesn't come, of course I'll leave it as is.
 

apokolok

2019-11-15 13:03:53
  • #4
Either you can and do it yourself or you trust the man.
Everything in between doesn't help much.
 

bierkuh83

2019-11-15 14:34:30
  • #5
Well, you don’t have a basement, as you’ve already recognized yourself, but then there will be an intermediate ceiling inspection before concreting. I would have him come again before the ring beam is poured. Basically, better to have him come once too often. The money invested can be worth its weight in gold, especially if you’re not familiar with it. But have a look at it beforehand and have the execution documents and construction performance description checked. The experts are all different. Ours from BHS was a bit clumsy, but he looked everywhere and questioned everything. Continue the inspection protocol until the end and attach it to the acceptance protocol. Discuss the procedure beforehand with the BL from the GU.
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
18.12.2013Which interior plaster to use for a concrete basement10
12.08.2014Construction method: Prefabricated house Solid house Construction supervisor Architectural planning18
24.08.2021Slope position, basement open at the front, bathtub31
11.10.2017Sealing on Styrodur insulation?14
09.12.2016Planning/Floor plan single-family house (approx. 140 sqm, basement, ground floor, attic)30
18.05.2020Proper Ventilation/Drying of Interior Plaster / Drying Time21
22.07.2017Horizontal sealing of the base slab24
18.08.2017Base plate ready - construction supervisor absent20
04.09.2017Sealing the garage with a concrete floor?21
18.05.2018Single-family house with >180 sqm / basement / garage68
14.10.2019Dampness in the basement on the floor slab and walls25
15.04.2019Missing sealing in bathrooms detected after 16 years.13
12.07.2023Sealing of floor-to-ceiling windows from the outside74
27.01.2020Building a single-family house with/without a basement on a small plot65
25.07.2020Single-family house 180 sqm, basement, 2 full floors + gable roof16
11.01.2021Basement or slab? - Cost estimation24
11.03.2021Building description for a single-family house with a basement42
10.07.2021Is basement waterproofing available in the old building from 1971?12
31.05.2025Floor plan single-family house 240 m², 2 full floors without basement, solid construction47

Oben