ich123
2012-06-20 22:05:49
- #1
[INDENT]Hello, we are currently building a single-family house in NRW through a construction company.
thankfully, the shell is already standing.
the whole project is still developing miserably, besides planning errors already at the beginning of the shell construction, now further mistakes are added, e.g. as contractually agreed, no soil investigation was carried out..
there is a scope of services description listing all building elements and also some construction companies which change afterwards or now during the construction phase...
there is also a payment schedule which, however, is not consistent with the scope of services description and does not adhere to all individual payment amounts..
thus the fixed price cannot be maintained either and we will probably have to pay a lot extra..
the construction company also only issues invoices and does not accept any of the trades, how could they.. no expert is available and there is nothing to gain.
now we are considering whether to terminate the whole project with the construction company and engage an architect who is already well-established in this building area..
he would take over our project and contractually complete everything..
with some skill we would get an overview of all companies and could obtain offers/trades to get an overview of the costs or the difference
the architect could take over construction management, i.e. could check the offers/tenders of the craftsmen and accept the work, that would probably be about 38% of the fee schedule ??
question to the experts: "what would the architect cost us for a planned house price of 153,100.00 euros or does the increased price apply then?
we would appreciate a little information and could then be sure that our current emergency situation is not further exploited...
thank you in advance
Regards, Marion
[/INDENT]
thankfully, the shell is already standing.
the whole project is still developing miserably, besides planning errors already at the beginning of the shell construction, now further mistakes are added, e.g. as contractually agreed, no soil investigation was carried out..
there is a scope of services description listing all building elements and also some construction companies which change afterwards or now during the construction phase...
there is also a payment schedule which, however, is not consistent with the scope of services description and does not adhere to all individual payment amounts..
thus the fixed price cannot be maintained either and we will probably have to pay a lot extra..
the construction company also only issues invoices and does not accept any of the trades, how could they.. no expert is available and there is nothing to gain.
now we are considering whether to terminate the whole project with the construction company and engage an architect who is already well-established in this building area..
he would take over our project and contractually complete everything..
with some skill we would get an overview of all companies and could obtain offers/trades to get an overview of the costs or the difference
the architect could take over construction management, i.e. could check the offers/tenders of the craftsmen and accept the work, that would probably be about 38% of the fee schedule ??
question to the experts: "what would the architect cost us for a planned house price of 153,100.00 euros or does the increased price apply then?
we would appreciate a little information and could then be sure that our current emergency situation is not further exploited...
thank you in advance
Regards, Marion