Osnabruecker
2021-11-26 08:42:00
- #1
Yes, it will go in that direction. Then you have to compare it with your contract, you only pay 0.50 excavation separately. How does the top edge of the finished floor look? The inspector has "accepted" it. If it fits into the surroundings, you could possibly plan the floor slab deeper? That would mean less delivery material... But that affects planning so deeply (considering outdoor facilities, etc.) that it might already be too late for that. Have the offer from the general contractor given to you, referring to the approx. 5,000 €... I’m curious whether there will be a 1 or 2 in front of it. If in doubt, get offers yourself. The service of the general contractor (removing 30 cm of soil) is minor; if in doubt, assign everything yourself including mostly disposal. Good luck!