I am new here in the forum, as I am currently tackling the construction of a turnkey KFW 55 house in Bonn. I would definitely appreciate your answers, as I still have many questions.

There are still a few preparations underway and soon it will start, and I am still considering whether I should register with the [Verband privater Bauherren] and hire a construction supervisor. Since it is a KfW 55 new building, we have already planned a KfW construction supervisor.

The question now is whether we should plan for an additional construction supervisor for further appointments?

1) Does anyone have experience with the [Verband privater Bauherren], preferably from Bonn? 2) Do you think one needs an additional construction supervisor besides the KfW construction supervisor? Honestly, I am unsure if the latter only focuses on the energy-efficient thermal insulation, etc. 3) If yes, for how many and which construction phases would you recommend this?

Thank you very much in any case. I would be grateful if someone would share their experiences.

Best regards

HHarms
 

Bookstar

2019-03-07 07:03:14
  • #2
Under no circumstances a construction supervisor, anyone in Germany can call themselves that. Therefore, most of them are also incompetent.

Find a proper expert or architect who supervises your construction.
 

Katdreas

2019-03-09 21:15:54
  • #3
We found someone who does both. He will come to the construction site a total of 20 times, and beforehand there was a construction meeting with [Gutachter,GU] and us.
 

Niloa

2019-03-09 21:45:24
  • #4
I once learned that an expert should be publicly appointed and sworn in to be competent.
 

Jana33

2019-03-12 19:36:00
  • #5
Well, there are idiots there too..... but I would definitely take an expert with me, because only they advise you independently and not in their own favor....
 

H.Harms

2019-03-15 23:15:19
  • #6
Hi, thanks already for the answers! How many appointments and for which construction phases would you recommend, should one bring in someone else besides the KFW construction supervisor (whom I need anyway for my KfW loan)?
 

Similar topics
19.06.2009Evaluation of the KfW 60 House Contract: Credit Check for House12
19.01.2013KfW 70 - which roller shutters in the new city villa?10
12.05.2014KfW 70 without ventilation system107
03.05.2011KfW loan okay or is there a cheaper option?10
21.08.2011Which heating system is suitable for our Kfw 70 house without a basement?15
10.07.2011Wall construction and insulation for Kfw 70 house, okay?19
07.10.2016Which heating is recommended for KfW 55?58
01.05.2019Assignment Declaration of Credit53
03.07.2014Costs for a house appraisal report due to damages11
06.07.2015Experiences with building surveyors12
17.02.2016KFW 55 in semi-heated basement - cold basement31
09.07.2016Construction supervision in the Dortmund area: Association of Private Builders or SV11
07.11.2017Building cheaply - this is how it can be done too!222
23.05.2025Is membership in the Association of Private Builders worthwhile?36
30.08.2019Expert: For which construction phases is it urgently necessary?51
23.06.2021House construction in Saxony, how do I plan realistically?48
28.10.2021External construction supervisors Berlin / Brandenburg towards West24

Oben