1.5 meters below the road edge

  • Erstellt am 2020-06-22 14:07:35

goalkeeper

2020-06-24 17:18:22
  • #1
We also had such a site (about 1.50m lower at the end terraced house) and that is quite difficult.

In our case, the entire area is also lower - none of the builders procured any material but took the leftover excavation from the neighbors.

However, you are also a bit dependent on the good neighbors. If they do not build in a timely manner, you cannot fill your entire plot and lay out the garden – or set L-bricks to the neighbors at a high cost.

We also compensated for our height difference with strip foundations - it was still more expensive than a slab foundation - but still several thousand euros cheaper than a basement. Also, you can check various platforms to see if someone in your region is giving away excavation for free. Often free including transport. Then you just need someone to install it for you.
 

Similar topics
11.07.2011Basement costs realistically without excavation and removal?21
27.08.2015Temporary storage of excavation from the neighbor's property?22
12.07.2017Excavation of construction pit - analysis of excavation material?12
02.10.2018Excavation for the basement, your opinion on the cubic meters31
02.04.2019Building plot: Massive fill or better basement with excavation?28
08.08.2022Costs for basement excavation without disposal21
22.11.2022Rough staking changed, excavation incorrect11

Oben