deichwacht
2016-11-14 13:29:28
- #1
Hello.
We are currently constructing a new building (KfW40) with exterior walls made of aerated concrete (17.5 cm), which will later be clad with bricks after the insulation is applied. At several points, relatively wide (about 1 cm) joints have formed where cut aerated concrete blocks meet, which are currently still open. The site manager does not see this as a problem. The gaps will later be mortared on the outside and sealed airtight on the inside by plastering.
Is the occurrence of such joints already considered a defect, or is it unproblematic? Will the insulation be affected by this? Is the planned procedure for sealing proper? Or must a different approach be taken?
Thank you very much!

We are currently constructing a new building (KfW40) with exterior walls made of aerated concrete (17.5 cm), which will later be clad with bricks after the insulation is applied. At several points, relatively wide (about 1 cm) joints have formed where cut aerated concrete blocks meet, which are currently still open. The site manager does not see this as a problem. The gaps will later be mortared on the outside and sealed airtight on the inside by plastering.
Is the occurrence of such joints already considered a defect, or is it unproblematic? Will the insulation be affected by this? Is the planned procedure for sealing proper? Or must a different approach be taken?
Thank you very much!