What do you think about this payment plan?

  • Erstellt am 2012-09-05 21:47:27

chrizzt

2012-09-05 21:47:27
  • #1
We received an almost final offer today. So far, so good. I would like to have your opinion on the payment schedule. The offer amount is approximately €190,000. We are building in the Berlin suburbs.

Planning installment €18,000
10 days after completion of the building application
Regarding the remaining payment amount, the installments are due as follows:


Construction installment 1: 38%
10 days after completion of the earthworks, construction of the foundations and slab, delivery and assembly of the wall elements and the roof truss
Construction installment 2: 23%
10 days after roof covering, delivery and installation of windows and patio door,
Construction installment 3: 13 %
10 days after completion of heating, sanitary and electrical work in shell construction and after the screed has been installed
Construction installment 4: 5 %
10 days after approximately 80% of the facing facade has been constructed
Construction installment 5: 8 %
10 days after approximately 80% of the contractor’s tile and painting work has been completed


Construction installment 6: 3 %
10 days after acceptance.
 

chrizzt

2012-09-06 18:04:40
  • #2
Thank you!!! I am surprised by the down payment... but maybe it has to be that way
 

Häuslebauer40

2012-09-07 07:45:59
  • #3
Well, 9.5% is okay. After all, it is only due 10 days after the completion of the building application documents. It would have been worse if they wanted the money earlier.
 

Baustratege

2012-09-15 12:47:31
  • #4

.. you are absolutely right ... I share the same opinion ...
 

Similar topics
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
08.08.2016Payment before or after completion of the construction phase?51
28.02.2017Are securities customary for completion and warranty?24
19.08.2018Strategically well-planned handover completion under building supervision11
29.09.2020Building permit before completion of development31
14.11.2021Sell an apartment from a two-family house immediately after completion34
01.07.2022Construction delay without completion. The house simply is not finished21

Oben