Thomas7
2020-06-28 21:41:52
- #1
Hello everyone,
the construction of our single-family house has just started – the foundation is finished and the first row of hollow bricks has been laid. I thought trust is good, but checking is better, so I measured all the rooms and brick positions. Compared to the construction plan, as created by the architect and approved by the building authority, I found various deviations and immediately informed my general contractor. He told me that everything is correct – the structural engineer had only made some changes for structural reasons. Indeed, it seems all of this is due to structural considerations, but now several walls are 17.5 cm thick instead of 11.5 cm (the architect had previously included some load-bearing 17.5 cm walls, but not so many). Overall, we lose 0.5 m² and some walls were shifted by 6 cm (to avoid protrusions).
This caught me off guard and is annoying in some places (e.g. narrower cross gable – placing a table here was already tight in terms of width and now it’s off by another 12 cm). We were never informed that something might change and even after the structural calculations, we were not told that something would definitely change...
My questions now are:
- Is this normal? Has this happened to you or were you informed beforehand?
- Do I have claims for defects or do I have to accept this (this is a bit general now, but maybe someone knows comparable cases? 0.5 square meters correspond roughly to about 1000€ construction cost...
Thanks in advance for your input...
the construction of our single-family house has just started – the foundation is finished and the first row of hollow bricks has been laid. I thought trust is good, but checking is better, so I measured all the rooms and brick positions. Compared to the construction plan, as created by the architect and approved by the building authority, I found various deviations and immediately informed my general contractor. He told me that everything is correct – the structural engineer had only made some changes for structural reasons. Indeed, it seems all of this is due to structural considerations, but now several walls are 17.5 cm thick instead of 11.5 cm (the architect had previously included some load-bearing 17.5 cm walls, but not so many). Overall, we lose 0.5 m² and some walls were shifted by 6 cm (to avoid protrusions).
This caught me off guard and is annoying in some places (e.g. narrower cross gable – placing a table here was already tight in terms of width and now it’s off by another 12 cm). We were never informed that something might change and even after the structural calculations, we were not told that something would definitely change...
My questions now are:
- Is this normal? Has this happened to you or were you informed beforehand?
- Do I have claims for defects or do I have to accept this (this is a bit general now, but maybe someone knows comparable cases? 0.5 square meters correspond roughly to about 1000€ construction cost...
Thanks in advance for your input...